Engineer | Form: (04 ) 401524786 5/21/2018 | This approval is good for one year and a new application must be made before January 24, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the TA request. |
Engineer | Form: (04 ) 401195875 5/21/2018 | This approval is good for one year and a new application must be made before January 27, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the TA request. |
Engineer | Form: (04 ) 401744863 9/18/2018 | This approval is good for one year and a new application must be made before January 24, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application. |
Engineer | Form: (04 ) 401873321 4/22/2019 | This approval is good for one year and a new application must be made before January 24, 2020(1 year from prior application). Updates for the planned utilization of the well should be included with the application. |
Engineer | Form: (04 ) 402269627 3/30/2020 | 1) This approval is good for one year and a new application must be made before 1/09/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
Engineer | Form: (04 ) 402561076 1/21/2021 | 1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
Engineer | Form: (04 ) 402909710 2/8/2022 | 1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. Please update production reporting status of all applicable months from SI to TA for 1/1999 forward. COGCC digital production reporting began in 1999 and does not go back to 1989.
3) Submit a current Wellbore Diagram on a Form 4 Sundry.
|
Engineer | Form: (04 ) 403746432 4/11/2024 | 1) For applicable operations , report work completed with a Form 4 Sundry REPORT OF WORK DONE - Repair Well noting final pressure test results and include any operational or job summaries. If the wellbore geometry changes or there is not an updated WBD in the well file submit an updated WBD.
2) For applicable operations, submit a Form 5A or 5 within 30 days of the work with job related documents including a minimum of one of the following attachments: operations summary, cement job summary and/or wireline summary. Additionally, include CBL’s and any additional logs run.
3) Complete a Form 21 MIT to verify repairs for injection wells |