UIC | Form: (05A ) 401734059 8/28/2018 | Tubing Plug means well is TA not just SI. Well must pass MIT by 11/30/2018 |
UIC | Form: (04 ) 401821331 11/5/2018 | Contact COGCC with update on progress by November 23, 2018. Email or telephone call acceptable. |
Engineer | Form: (04 ) 403608206 11/28/2023 | 1) For applicable operations , report work completed with a Form 4 Sundry REPORT OF WORK DONE - Repair Well noting final pressure test results and include any operational or job summaries. If the wellbore geometry changes or there is not an updated WBD in the well file submit an updated WBD.
2) For applicable operations, submit a Form 5A or 5 within 30 days of the work with job related documents including a minimum of one of the following attachments: operations summary, cement job summary and/or wireline summary. Additionally, include CBL’s and any additional logs run
3) Complete a Form 21 MIT to verify repairs for injection wells
|