Engineer | Form: (04 ) 402621813 4/19/2021 | 1) This sundry to conduct bradenhead diagnostic evaluations is valid until 3/5/2022
2) For Wells that have sustained casing pressure above the action threshold as determined through diagnostic testing and evaluation, the Operator will provide a PMP with the Form 4, including a description of the Operator’s findings from the previous year, number of times the well was blown down, a current WBD and future plans for more frequent monitoring or testing, pressure mitigation, or remedial well work by 3/5/2022
3) Bradenhead bleed off is required to be in compliance with COGCC and CDPHE regulations. |
Engineer | Form: (04 ) 402971349 3/8/2022 | Most recent BH test completed on 6/11/2021 had a starting pressure below the threshold of 183 psi.
The attached plot shows the BH pressure over the last 12 months and it did not exceed the threshold pressure |