TypeSource DocumentConditions of Approval
UICForm: (04 )
400808437
3/13/2015
Operator required to perform MIT at minimum of 1200 psi if well is to be returned to production.
UICForm: (04 )
400808437
3/13/2015
Well required to pass a witnessed MIT at minimum of 350 psi after setting packer and prior to converting well for monitoring. Last witnessed MIT passed on April 12, 2010 had pressure loss (790 to 750 psi) but <10%.
UICForm: (04 )
400808437
3/13/2015
Permission is granted for setting isolation packer at 5720 ft. Wellbore diagram shows another type of packer at 5896 ft in the 7" casing string, 43 ft above 4-1/2 inch liner.
EngineerForm: (04 )
401522990
2/8/2018
This approval is good for one year and a new application must be made before January 13, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application. A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
EngineerForm: (04 )
401744386
9/18/2018
This approval is good for one year and a new application must be made before January 13, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
EngineerForm: (04 )
401872179
4/18/2019
This approval is good for one year and a new application must be made before January 13, 2020(1 year from prior application). Updates for the planned utilization of the well should be included with the application. A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request and the related Form 5A reporting.
EngineerForm: (04 )
402264455
3/26/2020
1) This approval is good for one year and a new application must be made before 1/9/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. 2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. 3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
EngineerForm: (04 )
402551754
1/25/2021
1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. 2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
EngineerForm: (04 )
402906518
2/3/2022
1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. 2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. 3) Submit a current Wellbore Diagram on a Form 4 Sundry
EngineerForm: (04 )
403844039
7/9/2024
1) For applicable operations , report work completed with a Form 4 Sundry REPORT OF WORK DONE - Repair Well noting final pressure test results and include any operational or job summaries. If the wellbore geometry changes or there is not an updated WBD in the well file submit an updated WBD. 2) For applicable operations, submit a Form 5A or 5 within 30 days of the work with job related documents including a minimum of one of the following attachments: operations summary, cement job summary and/or wireline summary. Additionally, include CBL’s and any additional logs run. 3) Complete a Form 21 MIT to verify repairs for injection wells
UICForm: (04 )
403844039
7/11/2024
Operator shall provide cement bond logs over liner and 7 inch casing string. Provide cement bond log and all other logs run with Form 4 Sundry REPORT OF WORK DONE.
UICForm: (04 )
403844039
7/11/2024
Packer depth shall be within 100 feet of top perforation.
UICForm: (04 )
403844039
7/11/2024
Mechanical Integrity Test shall be witnessed before the commencement of injection. Provide at least 10 day notice via Form 42.
 