| Engineer | Form: (02) 400611165 05/23/2014 | (1) COMPLIANCE WITH THE MOST CURRENT REVISION OF THE NORTHWEST COLORADO NOTIFICATION POLICY IS REQUIRED. SEE ATTACHED NOTICE. |
| Engineer | Form: (04) 401530073 05/22/2018 | This approval is good for one year and a new application must be made before January 30, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the TA request. |
| Engineer | Form: (04) 401747797 09/18/2018 | This approval is good for one year and a new application must be made before January 30, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application. |
| Engineer | Form: (04) 402070310 07/03/2019 | This approval is good for one year and a new application must be made before January 30, 2020. Updates for the planned utilization of the well should be included with the application. |
| Engineer | Form: (04) 402269672 03/30/2020 | 1) This approval is good for one year and a new application must be made before 1/09/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
| Engineer | Form: (04) 402561615 01/25/2021 | 1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 402947045 02/07/2022 | 1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. |
| Engineer | Form: (04) 403210327 03/01/2023 | Updated well classification to Observation Well. Used 11/04/2022 as date well is no longer an injector. Operator to report this well as AC (Active) on Form 7. |