Engineer | Form: (04 ) 401514047 3/21/2018 | This approval is good for one year and a new application must be made before January 16, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. |
Engineer | Form: (04 ) 401705581 8/17/2018 | This approval is good for one year and a new application must be made before January 16, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated
interval. |
Engineer | Form: (04 ) 401870637 4/16/2019 | This approval is good for one year and a new application must be made before January 16, 2020(1 year from prior application). Updates for the planned utilization of the well should be included with the application. |
Engineer | Form: (04 ) 402269687 3/31/2020 | 1) This approval is good for one year and a new application must be made before 1/09/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
Engineer | Form: (04 ) 402562409 1/12/2021 | 1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. |
Engineer | Form: (04 ) 402910281 2/9/2022 | 1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. Please update production reporting status of all applicable months from SI to TA for 1/2004 forward.
3) Submit a current Wellbore Diagram on a Form 4 Sundry
|