| Agency | Form: (02) 2095799 03/19/2010 | 1) Provide 24 hour notice of MIRU to Craig Quint at 719-767-8939 or e-mail at craig.quint@state.co.us. 2) If production casing is set ensure cement coverage of Cheyenne/Dakota interval (5250’-4600’ minimum). Run and submit CBL to verify all cemented intervals. 3) If well is a dry hole set plugs at the following depths: 40 sks cement +/- 50’ above the Cherokee, 40 sks cement across any DST w/ show, 40 sks cement 100’ below Cheyenne (5250’ up), 40 sks cement 50’ above top of Dakota (4600’ up), 50 sks cement from 50’ below surface casing shoe up into surface casing, 15 sks cement in top of surface casing, cut 4 ft below GL, weld on plate, 5 sks cement each in rat hole and mouse hole. |
| Engineer | Form: (02) 400293219 08/16/2012 | 1) Provide 48 hour notice prior to spud via electronic Form 42.
2) If production casing is set provide cement coverage to at least 200’ above shallowest completed interval and across Cheyenne/Dakota interval (5100’-4600’ minimum). Run and submit CBL to verify cemented intervals.
3) If well is a dry hole set plugs at the following depths: 40 sks cement +/- 50’ above the Lansing, 40 sks cement across any DST or significant show, 40 sks cement at 5100’ up, 40 sks cement at 4600’ up, 50 sks cement from 50’ below surface casing shoe up into surface casing, 15 sks cement in top of surface casing, cut 4 ft below GL, weld on plate, 5 sks cement each in rat hole and mouse hole.
|
| Permit | Form: (05) 2238051 01/25/2013 | As-drilled GPS must be provided prior to plugging this well. |
| Engineer | Form: (04) 400692351 10/14/2014 | 1) The flaring of natural gas shall be conducted in accordance with COGCC Rule 912.
2) Notify the local emergency dispatch or the local governmental designee of any natural gas flaring.
3) If flaring will continue more than 6 months, submit updated requests to flare to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring.
4) The operator is required to obtain and maintain any required air permits from CDPHE.
5) The venting or flaring volumes shall be reported by Form 7, Operator’s Monthly Report of Operations.
|
| Engineer | Form: (04) 400982437 03/25/2016 | 1) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
2) Venting or flaring of natural gas shall comply with COGCC Rule 912.
3) Report flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) Notify the local emergency dispatch or the local governmental designee of natural gas flaring.
5) The operator is required to obtain and maintain any required air permits from CDPHE. The combustion device must comply with applicable design destruction efficiency for hydrocarbons.
|
| Engineer | Form: (04) 401216593 04/26/2017 | 1) Venting or flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
3) Report flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from CDPHE. The combustion device must comply with applicable design destruction efficiency for hydrocarbons (typically enclosed device 98%).
|
| Engineer | Form: (04) 401543682 08/24/2020 | Presence of hydrogen sulfide should be reported on a Form 42, Field Operations Notice. |
| Engineer | Form: (04) 401543682 08/24/2020 | The expectation for permanent flares controlling separators will be an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. Operator shall manage this well so that production volumes do not exceed the combustor capacity. |