| Engineer | Form: (06) 401246097 03/31/2017 | Prior to initiation of plugging operations, a Bradenhead test shall be performed. If there is 25# or greater present at the beginning of the test call COGCC Engineer for possible sampling requirements. Form 17 shall be submitted within 10 days. |
| Engineer | Form: (06) 401246097 03/31/2017 | NOTE: Changes in plugging procedure - shoe plug moved to 590'
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) If shoe plug not circulated to surface (or falls back) - tag plug, must be 150' or shallower and place 10 sx at surface (or top off).
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
|