WELL05-069-06114HALE
3
MAGPIE OPERATING INC
52530
PA
11/30/2023
LOVELAND
52000
LARIMER  069
SWSE 31 5N68W 6
307132View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04 )
402632765
4/26/2022
Effective Apr 30, 2022 this well will be designated inactive and must be properly returned to production, plugged, have an approved 5B or added to a Form 6A list no later than November 1, 2022.
EngineerForm: (04 )
403093988
7/7/2022
1) This well is designated inactive and must be properly returned to production, plugged and abandoned, have an approved Form 5B or be submitted on a Form 6A (to be designated as Out of Service) no later than no later than November 1, 2022. 2) The Form 7, Operators Report of Monthly Operations, must correctly reflect the well status.
OGLAForm: (06 )
403437333
8/2/2023
This oil and gas location is within 0.5-mile of a CPW-mapped bald eagle nest area. Plugging and abandonment (P&A) should not occur from December 1 to July 31. If site conditions warrant that P&A activities must be performed from December 1 to July 31, Operator will consult with the regional CPW Energy Liaison to develop site specific measures to avoid, minimize, or mitigate impacts to wildlife. CPW Consultation attached by operator.
OGLAForm: (06 )
403437333
8/2/2023
Due to close proximity to Residential Building Units (RBUs): prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of RBUs that are nearby and adjacent to the parcel on which the well is located. The sheet will include the operator's contact information and the nature, timing, and expected duration of the P&A operations.
OGLAForm: (06 )
403437333
8/2/2023
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. Due to the proximity of residential building units (RBUs) all blowdown gasses will be controlled.
OGLAForm: (06 )
403437333
8/2/2023
Due to proximity of plugging and abandonment (P&A) operations to BUs, operator will comply with Table 423 Maximum Permissible Noise Levels for residential land use. Prior to initiating work, operator will install temporary sound walls, straw bales, or other BMPs to dampen noise if necessary for compliance.
EngineerForm: (06 )
403437333
8/17/2023
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) Pump surface casing shoe plug at 261' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 161' or shallower and provide a minimum of 10 sx plug at the surface. 3) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation. 4) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
EngineerForm: (06 )
403437333
8/17/2023
Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for an ECMC Spill/Release Report, Form 19, associated with the abandoned line.
EngineerForm: (06 )
403437333
8/17/2023
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples. If there is a need for sampling, contact ECMC engineering for verification of plugging procedure.
EngineerForm: (06 )
403437333
8/17/2023
CHANGE IN PROCEDURE Lowered surface plug from 250' to 261' Operator concurs
 
COGIS - Best Management Practice Results