Engineer | Form: (06 ) 401252458 4/11/2017 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) For 550’ plug (surface casing shoe plug), if not circulated to surface then tag plug – must be 200’ or shallower and provide 10 sx plug at the surface.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete. |
Engineer | Form: (06 ) 401252458 4/11/2017 | Prior to initiation of plugging operations, a Bradenhead test shall be performed. If there
is 25# or greater present at the beginning of the test call COGCC Engineer for possible
sampling requirements. Form 17 shall be submitted within 10 days. |