WELL05-069-06082FT. COLLINS MUDDY UNIT
30-4
PROSPECT ENERGY LLC
10312
PA
3/28/2017
FORT COLLINS
25100
FORT COLLINS/LARIMER  069
NESE 30 8N68W 6
307113View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (06 )
2226144
3/15/2017
Cement Bond Log referenced should be submitted with Subsequent Report of Abandonment.
EngineerForm: (06 )
2226144
3/15/2017
Prior to initiation of plugging operations, a Bradenhead test shall be performed. If there is 25# or greater present at the beginning of the test call COGCC Engineer for possible sampling requirements. Form 17 shall be submitted within 10 days.
EngineerForm: (06 )
2226144
3/15/2017
1) Provide 48 hour notice of plugging MIRU via electronic Form 42. 2) For 450’ shoe plug: perforate, pump plug and displace. If surface casing shoe plug not circulated to surface then tag plug – must be 230’ or shallower and provide 10 sx plug at the surface (inside and outside of casing). 3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
 