COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02)
400196198
09/06/2011
1)COMPLIANCE WITH THE MOST CURRENT REVISION OF THE NORTHWEST COLORADO NOTIFICATION POLICY IS REQUIRED. 2)GARFIELD COUNTY RULISON FIELD NOTICE TO OPERATORS. NOTE: ALL NOTICES SHALL BE GIVEN VIA E-MAIL. SEE ATTACHED NOTICE 3)THE PROPOSED SURFACE CASING IS MORE THAN 50' BELOW THE DEPTH OF THE DEEPEST WATER WELL WITHIN 1MILE OF THE SURFACE LOCATION WHEN CORRECTED FOR ELEVATION DIFFERENCES. THE DEEPEST WATER WELL WITHIN 1 MILE IS 000 FEET DEEP.
EngineerForm: (02)
400466762
09/10/2013
(1) COMPLIANCE WITH THE MOST CURRENT REVISION OF THE NORTHWEST COLORADO NOTIFICATION POLICY IS REQUIRED. (2) COMPLIANCE WITH THE MOST CURRENT REVISION OF THE GARFIELD COUNTY RULISON-FIELD NOTICE TO OPERATORS IS REQUIRED.
PermitForm: (02)
401410904
01/30/2018
Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017).
EngineerForm: (02)
401410904
03/02/2018
1) Operator shall comply with the most current revision of the Northwest Notification Policy. 2) Operator shall comply with the most current revision of the Garfield County Rulison Field Notice to Operators, with the following exception: All field notice requirements specified in that Notice to Operators are superseded by the requirements of the most current revision of the Northwest Colorado Notification Policy (see Condition of Approval #1). 3) Operator shall provide cement coverage from the production casing shoe (4+1/2" First String) to a minimum of 200' above the Wasatch G formation. Adjust cement quantities as needed. Verify production casing cement coverage with a cement bond log. 4) The Operator shall monitor the bradenhead pressure of the proposed well and all offset wells under Operator’s control which penetrate the stimulated formation and have a treated interval separation of 300 feet or less. Monitoring shall occur from 24 hours prior to stimulation and shall continue until 24 hours after stimulation is complete. Recording shall be at a frequency of at least once per 24 hours with the capability of recording the maximum pressure observed during each 24 hour period. Operator shall notify COGCC Engineering staff if bradenhead pressures increase by more than 200 psig.
EngineerForm: (04)
403307366
02/27/2023
1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report 2) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method. 3) Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan 4) Complete installation of BH monitoring system by 5/31/2023
EngineerForm: (04)
403452381
09/06/2023
1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report or other Director approved submittal method. 2) Comply with any CDPHE, Air Pollution Control Division rules or requirements for all atmospheric discharges. 3) Any liquids blown down are to be collected, stored, handled, and treated or disposed as E&P waste per COGCC’s 900 series rules
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (02 )
401410904
3/9/2018
The first well drilled on the NPR H15 Pad will be logged with an open-hole Resistivity Log and Gamma Ray Log from TD into the surface casing. All wells on the pad will have a Cement Bond Log with cased-hole Gamma Ray run on the production casing. The Form 5 Completion Report will list all the logs run in the subject well and identify the well that was logged with the open-hole Resistivity Log.
Drilling/Completion OperationsForm: (02 )
401410904
3/9/2018
Closed loop system will be used. No pits will be built. Caerus will ensure 110 percent secondary containment for any potential volume of fluids that may be released.