| Agency | Form: (02) 400018310 01/26/2010 | 1)24 HOUR SPUD NOTICE REQUIRED. E-MAIL: david.andrews@state.co.us 2)GARFIELD COUNTY RULISON FIELD NOTICE TO OPERATORS. NOTE: ALL NOTICES SHALL BE GIVEN VIA E-MAIL. SEE ATTACHED NOTICE 3)CEMENT TOP VERIFICATION BY CBL REQUIRED. 4)THE PROPOSED SURFACE CASING IS MORE THAN 50' BELOW THE DEPTH OF THE DEEPEST WATER WELL WITHIN 1MILE OF THE SURFACE LOCATION WHEN CORRECTED FOR ELEVATION DIFFERENCES. THE DEEPEST WATER WELL WITHIN 1 MILE IS 000 FEET DEEP. |
| Engineer | Form: (04) 403179577 09/28/2022 | 1) Repair or plug well by 2/1/2023
2) Submit a Form 4 Repair Sundry for well work
3) Complete a bradenhead test following completion of the repair and submit results on a Form 17 or directive approved method |
| Permit | Form: (06) 403357003 04/03/2023 | Submit a form 5A to report the bridge plug identified on the wellbore diagram attached to the Notice of Intent. This Form 5A must be submitted within 30 days for compliance with Rule 416. |
| Engineer | Form: (06) 403357003 05/08/2023 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations.
2) The approved Form 6, Notice of Intent will be at the location during all phases of plugging operations.
3) Operator shall implement measures to control venting and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard.
4) If applicable properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Work plans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
5) Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
6) This well has federal minerals. Operator shall notify COGCC engineering staff of any plugging changes required by the BLM or unexpected conditions in the field as soon as feasible. Primary contact is Aaron Katz at 970-765-6300. Alternate COGCC contact is Craig Burger at 970-319-4194.
|