WELL05-045-14208PUCKETT
31D-24D
QB ENERGY OPERATING LLC
10844
PA
3/29/2024
GRAND VALLEY
31290
GARFIELD  045
NENE 24 6S97W 6
335463View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (06)
403382669
07/28/2023
This oil and gas location is within CPW-mapped Greater Sage-Grouse Priority Habitat Management Area (PHMA). CPW recommends that disturbance activities occur outside the period from March 1 to July 15 to protect the lekking, nesting, and brood-rearing periods for greater sage-grouse.
OGLAForm: (06)
403382669
07/31/2023
If activities must occur during the period from March 1 to July 15, operator will only operate during daylight hours.
EngineerForm: (06)
403382669
09/11/2023
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) The approved Form 6, Notice of Intent will be at the location during all phases of plugging operations. 3) Operator shall implement measures to control venting and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard. 4) Prior to placing surface shoe plug verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders. 5) If applicable properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Work plans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines. 6) Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples. 7) With the Form 6 SRA operator must provide written documentation, which positively affirms each COA listed above has been addressed.
 