Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-045-12477CSF
14C-08-07-91
TEP ROCKY MOUNTAIN LLC
96850
SI
1/1/2025
MAMM CREEK
52500
GARFIELD  045
SESW 8 7S91W 6
335054View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (04)
400599950
06/29/2014
PIPELINES: The following conditions of approval (COAs) will apply to the Form 4 if any temporary surface (poly/steel) or buried (poly or steel) pipelines are used during operations at the temporary frac pad location or nearby well pads: Operator shall pressure test pipelines in accordance with Rule 1101.e.(1) prior to putting into initial service any temporary surface or permanent buried (steel/poly) pipelines and following any reconfiguration of the pipeline network. Operator will utilize, to the extent practical, all existing access and other public roads, and/or existing pipeline right-of-ways, when placing/routing temporary surface pipelines.
OGLAForm: (04)
400599950
06/29/2014
DRILLING/COMPLETIONS: The following conditions of approval (COAs) will apply: Flowback and stimulation fluids generated at the well pads being serviced by this temporatory frac tank pad location must be sent to tanks, separators, or other containment/filtering equipment on the pad where fracing is taking place, before the fluids can be placed into any pipeline or storage vessel located on the well pad; or into the operator's pipelines or into tanker trucks for offsite disposal. A spill response trailer will be on location 24 hours a day, 7 days a week during construction and completion operations to facilitate a timely response to any spills that may occur. Appropriate heavy equipment (e.g., a backhoe) will be staged nearby and available at the location during all completion operations so that any emergency diversions or pits to contain spills can be built immediately upon discovery. All personnel working at the location during all drilling and completion operations will receive training on spill response and reporting. Documentation of this training will be maintained in the operator’s office/onsite trailer. At a minimum, weekly spill prevention meetings will be held identifying staff responsibilities in order to provide a quick and effective response to a spill. Appropriate documentation will be maintained in the operator’s office/onsite trailer. Operator will conduct daily inspections of equipment for leaks and equipment problems with appropriate documentation retained in the operator’s office/onsite trailer. All equipment deficiencies shall be corrected. Daily monitoring should end approximately 14 days after well completion and/or after production has been stabilized; however, timely inspections should continue during the production phase. Operator shall have trained personnel present at the frac tanks during water transfer into or out of tanks; personnel shall be able to shut off transfer pumps or close valves as necessary in response to upset conditions. Additional containment shall be required where temporary or permanent pumps and other necessary equipment or chemicals are located on the frac pad site. Operator will use adequately sized containment devices for all hazardous chemicals and/or materials stored or used on location. Operator will implement measures to ensure that adequate separation of hydrocarbons from the influent occurs to prevent accumulation of oil on the surface of stored fluids. Operator shall also employ a method for monitoring buildup of phase-separated hydrocarbons on the surface of stored fluids.
OGLAForm: (04)
400599950
06/29/2014
PLANNING: The following conditions of approval (COAs) will apply: Notify the COGCC 48 hours prior to start of temporary frac tank pad reconstruction/regrading, tertiary containment construction (if required), pipeline testing, and start of hydraulic stimulation operations using Form 42 (the appropriate COGCC individuals will automatically be email notified, including the LGD for hydraulic stimulation operations). Concurrent with notice required by Rule 316C., operator shall provide Form 42 notification to COGCC for this Oil and Gas Location when fracing operations will be supported by this pad. Operator shall prepare an emergency spill response program that includes employee training, safety, and maintenance provisions. In the event of a spill or release, the operator shall immediately implement the emergency response procedures in the above-described emergency response program. Use of this Oil and Gas Location for the purposes of a temporary remote frac pad is not permitted beyond December 31, 2014.
EngineerForm: (06)
404614523
04/23/2026
Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line.
EngineerForm: (06)
404614523
04/23/2026
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
EngineerForm: (06)
404614523
04/23/2026
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
EngineerForm: (06)
404614523
04/23/2026
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) Prior to placing cement above the surface casing shoe. Verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders. 3) Pump surface casing shoe plug only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug 4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation. 5) After surface plug and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years. 6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. 7) This well has federal minerals. Operator shall notify ECMC engineering staff of any plugging changes required by the BLM or unexpected conditions in the field prior to continuing operations.
OGLAForm: (06)
404614523
04/24/2026
Due to proximity to a wetland, surface water and expected shallow groundwater, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the wetland and surface water.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (04 )
400599950
6/30/2014
BACKGROUND • Ursa Operating Company LLC (Ursa) acquired all assets previously held by Antero Resources and assumed full operations on 4/1/13. • This location is an approved, constructed and producing location, and interim reclamation has been completed. • As these locations are on Federal (BLM) managed lands; there are no building units within 1000’. BLM has primary jurisdiction on Federal surface; as such BMPs and mitigation required by the BLM will be complied with. • BLM and Ursa conducted a joint onsite on April 4, 2014 and confirmed that the well pads being drilled and the temporary completions facility areas are within the scope of impacts assessed under the BLM Environmental Assessment for the Castle Springs field. • The location was permitted and constructed prior to Form 2A regulations being implemented. Therefore these BMPS focus on those required for placement, operations, and removal of the temporary completions tanks to support completions at an adjacent location; and not on construction, drilling, completions and production operations specific to this location. • Temporarily staging the tanks at this location does not require a pad expansion, addition of wells, installation of a pit, or significant change in the pad design or use essential to lease operations; as the temporary tanks will be placed in the same approximate location as if completions were supporting drilling at the same location (see attached diagram). • The only change is that staging temporary completions tanks at this location will support completions at the Castle Springs E (4 wells) & Q pads (2 wells) vs. the location on which they are temporarily staged; which is a standard practice recognized by the COGCC and other state agencies to avoid the need for additional surface disturbance. • Use of this locations was identified in the Form 2A submitted on March 10, 2014 as needed to support completions at the Castle Springs E & Q pads. Use of this location eliminates the need for additional temporary disturbance at the E & Q pads. • The temporary completions facilities are anticipated to be in use from late August through mid-October (approximately 60 days). • A maximum number of 20 - 500 bbl tanks will be temporarily staged at this location. • Existing buried water lines will be used to transfer water between the temporary completions facilities and the Castle Springs E & Q, minimizing traffic, noise, dust, truck air emissions, potential for accidents, and other environmental concerns. • The location is not within a 317B area. • Raptor surveys were conducted and nests were located in close proximity to this well pad. However, completions activities will not occur until after the nesting season (August).
Pre-ConstructionForm: (04 )
400599950
6/30/2014
TEMPORARY COMPLETIONS FACILITIES - PRE-OPERATIONS • Ursa will hold a pre-completions meeting with contractors using Ursa’s checklists prior to startup of activities. Ursa’s temporary completions facilities protocol will be discussed and implemented. • The tanks (cleaned and sanitized) will be placed at the location prior to startup and will be labeled as out of service until tanks are being filled and used, then properly labeled for use. • Prior to filling the tanks and placing them in use, Ursa shall provide Form 42 notification to COGCC in accordance with NTO’s when operations will be supported by this pad. Ursa will also notify the COGCC 48 hours prior to start of temporary frac operations. • Secondary Containment – Prior to filling the tanks, Ursa will install secondary containment for fluids contained in the temporary tanks. The containment would accommodate at least the volume of the manifolded volume and 150% of the largest tank; including, but not limited to, construction of a berm immediately adjacent to the tanks. This is based on Ursa’s temporary completions facilities protocol.
General HousekeepingForm: (04 )
400599950
6/30/2014
ENVIRONMENTAL STEWARDSHIP AND COMPLIANCE (GENERAL) • AIR / ODORS – Ursa will comply with CDPHE Air Regulations 3, 6 and 7, and COGCC Section 600 and 800 rules regarding green completions as required, and controlling air emissions from the tanks, minimizing the potential for odors. • CHEMICAL & MATERIAL HANDLING – All materials and chemicals will be managed to minimize environmental contamination. All chemicals used will be reported in accordance with COGCC Section 200 rules and policies; including entries to Frac Focus. • SPCC / COGCC SECONDARY CONTAINMENT - Ursa developed and implemented a site-specific Spill Prevention, Control and Countermeasures Plan (SPCC) for temporary completions facilities in accordance with EPA SPCC regulations (40 CFR 112) and COGCC Section 600 regulations, prior to placement of tanks at the location. In addition Ursa conducts monthly leak and spill visual inspections under its SPCC plan for temporary completions facilities. • SPILLS / INCIDENTS – Spill prevention and response are outlined in Ursa’s Spill Prevention and Management Plan (attached). This includes training of employees and contractors personnel. Spills response includes notifications, reporting, response actions, remediation and corrective actions. The spill criteria in Ursa’s plan require that waste be properly classified as E&P or non-E&P wastes. For E&P waste, all spills greater than 1 barrel (not within containment) or 5 bbls within containment will be reported to the COGCC using a Form 19. Should remediation be required, a Form 27 will be submitted upon COGCC request, outlining the proposed remediation. Spills related to non-E&P waste will be managed in accordance with CDPHE and EPA regulations depending on the volume spilled. • SPILL RESPONSE - Ursa currently stages spill response equipment and materials onsite. If additional response equipment is needed, equipment and materials, including Vac truck, backhoes are approximately 20 minutes away. Ursa requires all key personnel to also be equipped with spill equipment for immediate use upon discovery of a release. Personnel trained in spill response are on call 24 hours a day, 7 days a week. Ursa’s Spill Prevention and Management Plan and Spill, among others, provide explicit detail including spill notification, reporting, response and prevention. • WASTE MANAGEMENT – The location will be managed in accordance with Ursa’s Waste Management Plan which incorporates COGCC Section 900 rules. Appendix L of Ursa’s Waste Management Plan specifically addresses temporary completions facilities. Containment will be designed to localize and minimize the potential for any exploration and production wastes, chemicals, fluids, etc. from leaving the location, including berms, barriers, and use of spill control materials. • PLANS - All plans referenced herein have been provided the COGCC on previous occasions and are available upon request, as updated.
Drilling/Completion OperationsForm: (04 )
400599950
6/30/2014
TEMPORARY WATER LINES TO SUPPORT TEMPORARY COMPLETIONS FACILITIES • Ursa will pressure test any surface lines in accordance with Rule 1101.e. (1) prior to putting into initial service any temporary surface or permanent buried (steel/poly) pipelines and following any reconfiguration of the pipeline network. • Ursa will use adequately sized containment devices for and hazardous chemicals and/or materials if stored or used on location.
Drilling/Completion OperationsForm: (04 )
400599950
6/30/2014
TEMPORARY COMPLETIONS FACILITIES - OPERATIONS • Ursa will implement its temporary completions facilities protocol (attached) that addresses equipment start up, operations, and decommissioning. The checklist ensures integrity of all pipelines, secondary containment necessary for equipment, and ensures all valves and fittings are inspected for leaks or deficiencies. It should be noted that changes may be necessary to this checklist as site specific actions may be necessary to ensure all equipment and operations satisfy COGCC rules and regulations. • Completions Equipment Inspections – Ursa will conduct daily inspections of tanks and equipment for leaks and equipment problems with appropriate documentation retained in the operator’s office/onsite office. All equipment deficiencies shall be corrected promptly. Daily monitoring will end once the tanks are decommissioned (cleaned and sanitized); approximately 14 days after use of the completions facilities. • Trained Personnel – Ursa shall have trained personnel present at the frac tanks during water transfer into or out of tanks; personnel shall be able to shut off transfer pumps or close valves as necessary in response to upset conditions in accordance with Ursa’s completions facilities protocol. • In addition, as outlined in Ursa’s Spill Prevention and Response Plan, SPCC plan (required by EPA), and protocols to comply with COGCC Section 600 containment rules, training is conducted for Ursa employees and contractors at least annually. This training was recently completed in accordance with SPCC regulations and COGCC spill regulations Nov 21, 2013, in January 2014, and again on April 3, 2014.