| Engineer | Form: (04) 401267237 06/12/2018 | This approval is good for one year and a new application must be made before April 25, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 401646789 06/26/2018 | This approval is good for one year and a new application must be made before May 21, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 402073176 05/27/2020 | 1) This approval is good for one year and a new application must be made before 6/13/2020 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
| Engineer | Form: (04) 402308597 10/21/2020 | 1) This approval is good for one year and a new application must be made before 2/11/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
| Engineer | Form: (04) 402590883 03/10/2021 | 1) This approval is good for one year and a new application must be made before 2/10/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 402939642 03/01/2022 | 1) This approval is good for one year and a new application must be made before 2/11/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. Correct production reporting status from AB to TA for all applicable months
3) Submit a current Wellbore Diagram on a Form 4 Sundry
|
| Engineer | Form: (06) 403030968 07/19/2022 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations.
2) The approved Form 6, Notice of Intent will be at the location during all phases of plugging operations.
3) Operator shall implement measures to control venting and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard.
4) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
5) Perform bradenhead test prior to MIRU if test has not been performed within six months of plugging or annual test has not been completed. Submit results on Form 17. Contact area environmental protection specialist for sampling and analysis requirements if initial bradenhead pressure is greater than 25 psi.
|