| Engineer | Form: (04) 404488188 01/21/2026 | 1) For applicable operations, report work completed within 30 days on a Form 4 Sundry REPORT OF WORK DONE - Repair Well noting final pressure test results and include any operational or job summaries. If the wellbore geometry changes or there is not an updated WBD in the well file submit an updated WBD.
2) For applicable operations, submit a Form 5 or 5A (updated packer and tubing depths) within 30 days of the work with job related documents including a minimum of one of the following attachments: operations summary, cement job summary and/or wireline summary. Additionally, include CBL’s and any additional logs run.
3) Complete a bradenhead test within 30 days of completing the repair and submit results on a Form 17
4) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations
5) Operator shall notify ECMC Engineering staff of changes and/or additional repair methods to the approved repair procedure.
6) Complete a pressure test to verify repairs. Submit documentation of pressure test on the applicable post work ECMC form.
7) Well to be repaired within 6 months of identifying the integrity issue (9/9/2025). Pressure is to be managed and mitigated until repair is complete.
|
| Engineer | Form: (04) 404488188 01/21/2026 | Prior to placing cement, run a CBL and notify ECMC Engineering staff to discuss plugging plans |
| Engineer | Form: (04) 404416579 01/21/2026 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Well to be plugged or repaired within 6 months of identifying integrity issue (9/9/2025). Pressure is to be managed and mitigated until plugging or repair is complete.
3. Shut in bradenhead pressure shall not exceed threshold pressure.
4. Complete a bradenhead test within 30 days of completing the repair and submit results on a Form 17
|
| Engineer | Form: (04) 404586471 04/06/2026 | Operator shall continue to monitor pressure and report to ECMC through annual testing. If monitored well conditions meet reaction threshold or indicate a deficiency, a new bradenhead test and sundry must be filed.
Subsequent sundries will be submitted in accordance with ECMC rules based on monthly monitoring or annual testing results |