| Agency | Form: (02) 2095130 03/03/2010 | 1) Provide 48 hour notice of MIRU to Mike Leonard at 719-767-2805 or e-mail at mike.leonard@state.co.us. 2) Set surface casing to at least 700’ per Rule 317d, cement to surface. 3) Comply with Rule 321. Run and submit directional survey from TD to surface. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well. 4) Comply with Rule 317.o. Temperature log may be run instead of CBL to verify cement coverage of intermediate casing. 5) If well is a dry hole, set 50 sks cement at surface casing shoe, 15 sks cement in top of surface casing, cut off casing 4’ below GL, weld on plate, 5 sks cement in rat hole & 5 sks cement in mouse hole. |
| Engineer | Form: (02) 400310887 09/18/2012 | Run CBL to determine TOC behind 7" casing. Submit with Form 5. |
| Engineer | Form: (04) 402563922 04/14/2021 | Well is overdue for MIT, well must be successfully MIT'd or plugged and abandoned by June 30, 2021. |
| Engineer | Form: (04) 402563922 04/14/2021 | Reapplication for continued temporarily abandoned status can only occur with a valid MIT, reapplication must occur prior to July 15, 2021. |
| Engineer | Form: (04) 403009679 04/19/2022 | Effective Apr 30, 2022 this well will be designated inactive and must be properly returned to production, plugged, have an approved 5B or added to a Form 6A list no later than November 1, 2022. |
| Engineer | Form: (06) 402564798 06/02/2023 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) Pump surface casing shoe plug at 720' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 620' or shallower and provide a minimum of 10 sx plug at the surface.
3) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
4) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
| Engineer | Form: (06) 402564798 06/02/2023 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| Engineer | Form: (06) 402564798 06/02/2023 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |