Engineer | Form: (02 ) 402589422 6/4/2021 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, 6 months after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
Engineer | Form: (02 ) 402589422 6/4/2021 | Operator acknowledges the proximity of the listed non-operated wells: Operator agrees to: provide mitigation option 3 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of these wells.
039-06482 Bennett 10-1
039-06356 Amoco 11-4
039-06386 UPRR-Whelchel 1-15 |
Engineer | Form: (02 ) 402589422 6/4/2021 | 1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 2 business day spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered. |
Engineer | Form: (02 ) 402589422 7/15/2021 | Operator acknowledges the proximity of the listed wells. Operator assures that this offset list will utilize Option 4 per the DJ Basin Horizontal Offset Policy. Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will assure that no well on the proposed pad will be hydraulically stimulated within 1500' of the listed well, 039-06153 Davidson #3 For all wells that are drilled with any portion within 1500' of 039-06153 Davidson #3. In the Form 5A comments, operator will (1) certify that this well has no treated interval within 1500' of the 039-06153 Davidson #3 , (2) provide the measured depth of the beginning and end points of any non-stimulated interval in this well that falls within 1500' of the 039-06153 Davidson #3 and (3) the distance to each offset well from these points. In other words, fully describe the excluded interval.
039-06153 Davidson 16-3 |
Permit | Form: (02 ) 402589422 8/10/2021 | COGCC COA: Operator will insure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed.
|
Permit | Form: (02 ) 402589422 8/12/2021 | If the location has not been built by the Form 2A (Doc 402245599) expiration date of 01/11/2024, Operator must apply for an OGDP and submit a Refile the Form 2A for approval prior to location construction. |
Engineer | Form: (02 ) 403846094 8/8/2024 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
2) If a delayed completion, a second test is required between 6-9 months after rig release and must be conducted prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact COGCC engineering for approval prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
Engineer | Form: (02 ) 403846094 8/8/2024 | Operator acknowledges the proximity of the listed non-operated wells: Operator agrees to: provide mitigation option 3 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) for the remediated wells, referencing the API number of the proposed horizontal well(s) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of these wells.
039-06153 Davidson 16-3
039-06386 UPRR-Whelchel 1-15 |
Engineer | Form: (02 ) 403846094 8/8/2024 | 1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 2 business day spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with a cement bond log. |
Permit | Form: (02 ) 403846094 10/8/2024 | In the event delayed operations are to occur, Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017) |
Permit | Form: (02 ) 403846094 10/8/2024 | Operator will ensure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed. |
Permit | Form: (02 ) 403846094 10/8/2024 | Operator will log two (2) additional well(s) with open-hole resistivity log with gamma-ray log from the kick-off point into the surface casing for the stratigraphically deepest wells on the pad for a total of three (3) wells logged during the second rig occupation of this location |