| Engineer | Form: (02) 400566196 05/07/2014 | 1) Note surface casing setting depth change from 500’ to 1840’. Increase cement coverage accordingly.
2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
3) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|
| Permit | Form: (02) 400566196 06/18/2014 | Open hole resistivity and gamma logs shall be run to describe the stratigraphy of the entire well bore and to adequately verify the setting depth of surface casing and aquifer coverage. On a multi-well pad, these open hole logs are only required on one of the first wells drilled on the pad and the Drilling Completion Report - Form 5 for every well on the pad shall identify which well was logged. |
| Engineer | Form: (06) 402523720 11/05/2020 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
| Engineer | Form: (06) 402523720 11/05/2020 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 2080' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 1741' or shallower and provide 10 sack plug at surface.
4) Leave at least 100’ of cement in the wellbore for each plug.
5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 90 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
7) After placing the shallowest hydrocarbon isolating plug (6850'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. |
| Engineer | Form: (06) 402523720 11/05/2020 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| DOW | Form: (06) 402523720 11/05/2020 | PLUGGING CHANGES
Add perforations at 3000' and pump 40 sacks leaving 15 sacks in the casing
Add perforations at 1300' and pump 40 sacks leaving 15 sacks in the casing
Add perforations at 700' and pump 40 sacks leaving 15 sacks in the casing
Modified cement volume on the plug at 2080' to 120 sacks
Operator concurs |