Engineer | Form: (04 ) 401672985 9/19/2018 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Metered flaring volumes must also be reported on the Operators Report of Monthly Operations, Form 7.
3) Until designated otherwise by CDPHE, this gas will be considered as gas coming from the separator. Therefore, the operator is required to obtain and maintain any required air permits from CDPHE for separator gas.
4) Operator will use an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. Wells are to be managed so that production volumes do not exceed combustor capacity.
5) Provide the local emergency dispatch or the local governmental designee prior notice of natural gas flaring by supplying them with the approved Sundry Notice and all attachments. If any changes are made regarding this Sundry or the flaring protocol, local government designee and emergency dispatch are to be notified prior to flaring when flaring can be reasonably anticipated, or as soon as possible, but in no event more than two (2) hours after the flaring occurs.
6) This approval is good for until October 1, 2019. A new application will be required to continue flaring be submitted.
|
Engineer | Form: (04 ) 402176811 5/19/2020 | 1) Flaring of natural gas shall comply with COGCC Rule 912.
2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice.
3) Report metered flaring volumes on Form 7, Operator’s Monthly Report of Operations.
4) The operator is required to obtain and maintain any required air permits from CDPHE.
5) The expectation for permanent flares controlling separators will be an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. Operator shall manage this well so that production volumes do not exceed the combustor capacity.
6) Notify the local emergency dispatch or the local governmental designee of natural gas flaring.
|
Engineer | Form: (04 ) 402176811 5/19/2020 | Additional requests will detail field development within 10 miles of this well and what infrastructure is in place and actions have been taken to access infrastructure. |
Engineer | Form: (04 ) 402176811 5/19/2020 | This approval is good for one year and new application must be made before October 1, 2020. Compliance with CDPHE requirements shall be documented at that time. |
Engineer | Form: (04 ) 402176811 5/19/2020 | Presence of hydrogen sulfide at the battery should be reported on a Form 42, Field Operations Notice. |