OGLA | Form: (06 ) 403427044 6/14/2023 | Due to proximity to surface water, Operator will review the stormwater program and implement stormwater BMPs and erosion control measures as needed to prevent fine-grained sediment and impacted stormwater runoff from entering surface water. |
Permit | Form: (06 ) 403427044 6/21/2023 | Submit “as drilled” GPS data on Subsequent Report of Abandonment. GPS data must meet the requirements of Rule 216. |
Engineer | Form: (06 ) 403427044 6/21/2023 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) Pump surface casing shoe plug at 900' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 61’ or shallower and provide a minimum of 10 sx plug at the surface.
3) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
4) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
Engineer | Form: (06 ) 403427044 6/21/2023 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
Engineer | Form: (06 ) 403427044 6/21/2023 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap. Allow 30 days for Director’s review of the Form 27; include the Form 27 document number on the Form 6 Subsequent. Any historic Spill or Release discovered beyond the excavation required to safely cut and cap, will be reported on a Form 19, Spill/Release Report. |