Engineer | Form: (04 ) 402813084 9/16/2021 | Operator will mitigate bradenhead pressure in a short surface casing well by plugging this well by 04/21/2022 |
Engineer | Form: (06 ) 402796720 9/22/2021 | CBL to be run prior to plugging to verify stage tool setting depth and existing coverage - submit to COGCC for verification of plugging orders. |
| Form: (06 ) 402796720 9/22/2021 | 3.) Prior to commencing operations, at a minimum, the operator will provide an
informational sheet to the owners/occupants of BUs that are adjacent to the parcel on
which the well is located. The sheet will include the operator's contact information and
the nature, timing, and expected duration of the P&A operations.
|
Engineer | Form: (06 ) 402796720 9/22/2021 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
| Form: (06 ) 402796720 9/22/2021 | 2.) Prior to commencing operations, the operator will contact the City and County of Broomfield to
coordinate posting signs at conspicuous locations if appropriate. The signs will indicate plugging and
abandonment (P&A) operations are being conducted, the well name, well location
information, and the Operator's contact information. Signs must not create a potential
traffic hazard. |
Engineer | Form: (06 ) 402796720 9/22/2021 | 1) Provide 2 business day notice of plugging MIRU via electronic Form 42.
2) After placing the shallowest hydrocarbon isolating plug (6800'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) Prior to placing the 1250' plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
4) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 247' or shallower and provide 10 sx plug at the surface.
5) Leave at least 100’ of cement in the wellbore for each plug.
6) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Work plans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
7) With the Form 6 SRA operator must provide written documentation, which positively affirms each COA has been addressed. |
| Form: (06 ) 402796720 9/22/2021 | 1.) Operator will implement measures to capture, combust, or control emissions to
protect health and safety, and to ensure that vapors and odors from well plugging
operations do not constitute a nuisance or hazard to public health, welfare and the
environment. Due to proximity of building units (BUs) all blowdown gases will be
controlled. |