| Engineer | Form: (04) 402890882 02/07/2022 | This approval is good for one year and a new application must be made before December 7, 2022. Updates for the planned utilization of the well should be included with the application.
|
| Engineer | Form: (04) 402890882 02/07/2022 | The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 402890882 02/07/2022 | Update production reporting from September, 2021 to the present to reflect TA status and not SI.
|
| Engineer | Form: (04) 402890882 02/07/2022 | Submit a Form 5A indicating when and how the well was TA’d. |
| Engineer | Form: (04) 403577824 11/20/2023 | This ER IJ well is designated out of service and cannot be returned to operation.
Monthly monitoring and annual testing of the bradenhead shall continue until this well is plugged and abandoned.
Production reporting needs to be corrected to reflect the TA status from the time the well became TA as reported on the Form 5A, by 12/15/23. |
| OGLA | Form: (06) 403738165 04/08/2024 | This oil and gas location is within CPW-mapped High Priority Habitat for Lesser Prairie Connectivity Zone and Estimated Occupied Range. Plugging and abandonment (P&A) activities should not take place from March 1 to July 15. If site conditions warrant that P&A activities must occur between March 1 and July 15, the operator will consult with CPW to develop site specific avoidance, minimization, or mitigation measures prior to conducting any activities. |
| OGLA | Form: (06) 403738165 04/08/2024 | Due to proximity to mapped surface water, Operator will review the stormwater program and implement stormwater BMPs and erosion control measures as needed to prevent fine-grained sediment and impacted stormwater runoff from entering surface water. |
| Engineer | Form: (06) 403738165 04/16/2024 | Plugging
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations.
2) Plugs and squeezes will be placed as stated in the Plugging Procedure section of the approved NOIA unless revised by COA or prior approval from ECMC is obtained.
3) The wellbore must be static prior to placing cement plugs which are to be a minimum of 100' in length for all but surface plugs. Mechanical isolation requires a 25' cement plug, minimum. For plugs not specified to be tagged, a tag is required if circulation is not maintained while pumping plug and displacing to depth. Wait on cement(WOC) a minimum of 4 hrs before tagging a plug. Tag at tops specified or shallower. Notify ECMC Area Engineer before adding cement to previous plug due to low cement top.
4) Place a 50' plug (minimum) at the surface, both inside the inner most casing and in all annular spaces. Surface plugs shall be circulated to surface or placed in such a way as to ensure the full 50' plug. Confirm cement to surface and complete isolation in all strings during cut and cap. After cut and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging recording. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6 SRA which method was used and what was observed. Retain records of final isolation test for 5 years.
5) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
6) Operator must wait a sufficient time on all plugs to achieve the intended design. If at any time during the plugging there is evidence of previously unreported pressure or fluid migration, contact ECMC Area Engineer before continuing operations.
7) Plugging procedure has been modified as follows,
Plug #1 - 4010', CIBP with 5 sx of cement,
Plug #2 - 3075-2920', 20 sx cement casing plug,
Plug #3 - 1960-0', 255 sx cement casing plug,
Plug #4 - 50' of cement at the surface in both the casing and the annulus per COA #4. |
| Engineer | Form: (06) 403738165 04/16/2024 | Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line. |
| Engineer | Form: (06) 403738165 04/16/2024 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. |
| Engineer | Form: (06) 403738165 04/16/2024 | Bradenhead Testing
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
If there is a need for sampling, contact ECMC engineering for verification of plugging procedure. |