| Engineer | Form: (02) 401192602 07/08/2017 | Operator acknowledges the proximity of the listed non-operated wells. Operator agrees to: provide mitigation option 4 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. Well is beyond the area expected to be affected during stimulation (reservoir has not previously been developed) and can be monitored during stimulation. DANIEL KISSLER #1-9 API# 005-06877; KISSLER, DAN #1-10 API # 005-06799; KISSLER DAN #2-10 API # 005-06864;
|
| Engineer | Form: (02) 401192602 07/08/2017 | 1) Bradenhead test shall be performed within 60 days of rig release and prior to stimulation. Test results shall be submitted on Form 17 within 10 days of test. 2) Bradenhead test shall be performed between 6 and 7 months after rig release and shall be submitted on Form 17 within 10 days of test. 3) Bradenhead test shall be performed within 30 days of First Production as reported on Form 5A and shall be submitted on Form 17 within 10 days of test.
|
| Engineer | Form: (02) 401192602 07/08/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad. 2) Comply with Rule 317.j. and provide cement coverage from TD” to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|