| Engineer | Form: (02) 400245266 02/09/2012 | 1) Provide 24 hour notice of MIRU to COGCC inspector Mike Hickey via e-mail at Mike.Hickey@state.co.us. Indicate Spud Notice in the subject line and provide the following information: Operator Name, Well Name and Number, API #, Spud Date, Contact Name, Contact Phone #, E-mail Address.
2) Comply with Rule 317.i and provide cement coverage from end of 7” casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| Engineer | Form: (02) 400267267 05/04/2012 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) Comply with Rule 317.i and provide cement coverage from end of 7” casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| Reclamation Specialist | Form: (04) 400890803 09/24/2015 | The approval of this Form 4 is an acknowledgement that the document and attachments were received. It is not an approval of the interim reclamation as the outcome of the methods will be determined on the ground during an inspection at a future date. |
| Engineer | Form: (04) 402575694 02/24/2021 | All gas volumes are to be metered and combusted with a device with a 98% design efficiency for hydrocarbon destruction. The flared volumes are to be reported in the Form 7, Monthly Report of Operations. |
| Engineer | Form: (04) 402575694 02/24/2021 | The approved productivity test is not to exceed 60 calendar days and the well is to be shut in if a gas capture plan or Sundry requesting to continue to produce without infrastructure has not been approved by that time. |
| Engineer | Form: (04) 402719396 02/25/2022 | Gas volumes for productivity test not reported on Form7, amend reporting. |
| Engineer | Form: (04) 403368533 04/10/2023 | If well is not producing by March 31, 2024, an official MIT will need to be done. |
| Data Entry | Form: (04) 403368533 04/10/2023 | Well has been designated Inactive as of 06/30/2021. Submit a Form 5B, Inactive Well Notice. |
| Engineer | Form: (04) 403667142 03/22/2024 | If well is not producing by March 31, 2025, an official MIT will need to be done.
|
| Engineer | Form: (04) 404000434 11/26/2024 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations.
2) Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. |