LocationLocation IDRelated Facilities
WELL05-005-06636TAMI STATE
1
BAYSWATER EXPLORATION & PRODUCTION LLC
10261
PA
2/19/2018
SIDEWINDER
77458
ARAPAHOE  005
NESW 24 4S62W 6
320702View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (06)
401428056
12/13/2017
NOTE: Changes in plugging procedure - casing to be pulled deeper at 1190', stub plug placed and shoe plug starts deeper at 690' (this plug intended to come to surface) 1) Provide 48 hour notice of plugging MIRU via electronic Form 42. 2) For 1190’ plug: pump plug and displace - tag plug – must be 1090’ or shallower. If surface casing shoe plug not circulated to surface then tag plug – must be 270’ or shallower and provide 10 sx plug at the surface. 3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
EngineerForm: (06)
401428056
12/13/2017
If there has not been a bradenhead test within 60 days of plugging this well, prior to starting plugging operations a bradenhead test shall be performed. If the well was not sampled as part of a prior test, it should be sampled if pressure is 25# or greater or flowed liquid in previous test. 1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. The Form 17 shall be submitted within 10 days of the test.
EngineerForm: (06)
401428056
12/13/2017
This well should be plugged by March 1, 2018.
 