Engineer | Form: (02 ) 400258998 3/24/2012 | Prior to recomplete, operator must: 1) Notify Jim Precup at 303-726-3822, perform Bradenhead Test and submit Form 17 prior to recomplete. 2) Verify existing cement from 2200’ to surface casing with a cement bond log. Provide cement bond log to COGCC for review. COGCC may require remedial cementing. Cement coverage required from 2000’ (DV tool) into the surface casing shoe. Verify remedial cement coverage with cement bond log. |
Engineer | Form: (06 ) 402265241 1/16/2020 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
Engineer | Form: (06 ) 402265241 1/16/2020 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 2050' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 683' or shallower and provide 10 sack plug at surface.
4) Leave at least 100’ of cement in the wellbore for each plug.
5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
7) After placing the shallowest hydrocarbon isolating plug (7400'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. |
Engineer | Form: (06 ) 402265241 1/16/2020 | If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed.
1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required, and the COGCC engineering staff must be contacted.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
3) If sampling is required contact COGCC engineering for a confirmation of plugging
requirements prior to placing any plugs.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting
Instructions.
The Form 17 shall be submitted within 10 days of the test. |
Engineer | Form: (06 ) 402265241 1/16/2020 | CBL to be run prior to plugging to verify stage tool setting depth and existing coverage - submit to COGCC for verification of plugging orders. |