Permit | Form: (02 ) 401526764 8/27/2018 | Operator will insure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore setback was completed. |
Engineer | Form: (02 ) 401526764 10/17/2018 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after setting surface casing.
Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) 6 months after rig release, prior to stimulation (delayed completions).
3) Within 30 days of first production, as reported on Form 5A.
|
Engineer | Form: (04 ) 403695824 2/27/2024 | If well is not producing by February 28, 2025, an official MIT will need to be done. |