Engineer | Form: (02 ) 401394360 8/25/2018 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after setting surface casing.
Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) 6 months after rig release, prior to stimulation (delayed completions).
3) Within 30 days of first production, as reported on Form 5A.
|
Engineer | Form: (02 ) 401394360 10/17/2018 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 3) and ensure all applicable documentation is submitted. Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Brighton Company 2 (001-08544)
Operator acknowledges the proximity of the listed wells. Operator assures that this offset list will utilize Option 4 per the DJ Basin Horizontal Offset Policy. Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will assure that no well on the proposed pad will be hydraulically stimulated within 700’ of the listed well(s).
Brighton Company 1 (001-08355)
For all wells that are drilled with any portion within 700’ of Brighton Company 1 (001-08355): In the Form 5A comments, operator will (1) certify that this well has no treated interval within 700’ of the BRIGHTON COMPANY 1 (001-08355), provide the measured depth of the beginning and end points of any non-stimulated interval in this well that falls within 700’ of the Brighton Company 1 (001-08355) and 3) the distance to each offset well from these points. In other words, fully describe the excluded interval.
|
Engineer | Form: (02 ) 401394360 10/17/2018 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 3) and ensure all applicable documentation is submitted. Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Brighton Company 2 (001-08544)
Operator acknowledges the proximity of the listed wells. Operator assures that this offset list will utilize Option 4 per the DJ Basin Horizontal Offset Policy. Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will assure that no well on the proposed pad will be hydraulically stimulated within 700’ of the listed well(s).
Brighton Company 1 (001-08355)
For all wells that are drilled with any portion within 700’ of Brighton Company 1 (001-08355): In the Form 5A comments, operator will (1) certify that this well has no treated interval within 700’ of the BRIGHTON COMPANY 1 (001-08355), provide the measured depth of the beginning and end points of any non-stimulated interval in this well that falls within 700’ of the Brighton Company 1 (001-08355) and 3) the distance to each offset well from these points. In other words, fully describe the excluded interval.
|