| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Noise Mitigation: Baseline noise monitoring and testing will be conducted prior to the commencement of construction. Sound mitigation will be designed based on the results of the study to meet or exceed COGCC noise requirements. During completion activities, onsite equipment shall be positioned to take full advantage of the sound mitigation measures provided by the sound walls, well pad grading, and surrounding topography. Sound wall(s) will remain in place through the end of completions operations. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Light sources during all phases of operations will be directed downwards and away from occupied structures. Permanent lighting will be installed around the facility to allow both the operator and haulers to conduct safe operations at night. All lights will be directed down toward the location or shielded. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Closed Loop System: A Closed Loop System will be used for drilling and fluid management. No reserve pit will be used. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Logging: One of the first wells drilled on the pad will be logged with open-hole Resistivity Log and Gamma Ray Log from the kick-off point into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured-while-drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run and have those logs attached. The Form 5 for a well without open-hole logs shall clearly state “No open-hole logs were run” and shall clearly identify (by API#, well name & number) the well in which open-hole logs were run. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Anti-Collision: PetroShare will perform an anti-collision evaluation of all active (producing, shut in, or temporarily abandoned) offset wellbores that have the potential of being within 150 feet of a proposed well prior to drilling operations for the proposed well. Notice will be given to all offset operators within 150 feet prior to drilling. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Drill Stem Tests: Not applicable. No drill stem tests are planned. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | BOPE for well servicing operations: Adequate blowout prevention equipment will be used on any servicing operations associated with this well. Backup stabbing valves shall be required on well servicing operations during reverse circulation. Valves will be pressure tested before each well servicing operation using both low-pressure and high-pressure fluid. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | BOPE Testing for Drilling Operations: BOPE tests will be done upon initial rig-up and once every 30 days during drilling operations, pressure testing of the casing string and each component of the BOPE will be performed to 70% of working pressure or 70% of the internal yield of the casing, whichever is less. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | BOPE: Ward will utilize drilling rigs with a minimum of a double ram and annular preventer. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Pit Level Indicators: Pit Level Indicators will not be needed as no pits will be used on location. |
| Drilling/Completion Operations | Form: (02 ) 401221377 8/5/2017 | Operator acknowledges and will comply with COGCC policy for Bradenhead Monitoring during Hydraulic fracturing treatments in the Greater Wattenberg Area dated May 29, 2012. |