WELL05-001-09789State of CO
1S-66-36-3225CH
EXTRACTION OIL & GAS INC
10459
PA
7/21/2023
THIRD CREEK
81800
ADAMS  001
SWNW 36 1S66W 6
435283View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02 )
400497790
11/11/2013
1) Note surface casing setting depth change from 800’ to 1490’. Increase cement coverage accordingly. 2) Submit Form 42 electronically to COGCC 48 hours prior to MIRU. 3) Comply with Rule 317.i and provide cement coverage from end of 7" to a minimum of 200' above Niobrara. Verify coverage with cement bond log. 4) Run and submit Directional Survey from TD to base of surface casing. The operator shall comply with Rule 321, and it shall be the operator’s responsibility to ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
EngineerForm: (02 )
400497790
11/11/2013
Operator acknowledges the proximity of the (STATE A #1 API# 001-06757; STATE A #3 API # 001-06805; STATE A #4 API # 001-06810; STATE A #5 API # 001-06824; STATE A #6 API # 001-06834 )wells. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
EngineerForm: (02 )
400497790
11/11/2013
Operator acknowledges the proximity of the non-operated CHAMPLIN 117 AMOCO #1 (API # 001-06917) well. Operator assures that this offset will be remediated per the DJ Basin Horizontal Offset Policy (option 3) or operator will address this well with mitigation option 4. Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
EngineerForm: (06 )
403369227
4/28/2023
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
EngineerForm: (06 )
403369227
4/28/2023
Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Reclamation SpecialistForm: (04 )
403981440
11/20/2024
Remediation Project #'s 17011 and 28722 remain active at the location and must be closed and approved to pass final reclamation at the location.
 
COGIS - Best Management Practice Results