Engineer | Form: (02 ) 2285269 11/4/2011 | Provide remedial cement from current TOC (~1140') 50' into surface shoe. |
Engineer | Form: (06 ) 401775629 11/16/2018 | Form 6, Subsequent Report of Abandonment wellbore diagram should document 2011 remedial cement. |
Engineer | Form: (06 ) 401775629 11/16/2018 | NOTE: Changes made to plugging procedure; CBL to be run prior to plugging to verify existing coverage across lower and upper Arapahoe (CBL from 1200' to surface) - submit to COGCC for verification of plugging orders. Additional plugs required.
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) For 1900’ plug: pump plug and displace - tag plug – must be 800’ or shallower. If surface casing shoe plug (670’) not circulated to surface then tag plug – must be 300’ or shallower and provide 10 sx plug at the surface (inside and outside of casing).
3) Properly abandon flowlines as per Rule 1105. File electronic Form 42 once abandonment complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line the operator must submit a Flowline Report, Form 44.
|
Engineer | Form: (06 ) 401775629 1/4/2019 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
Engineer | Form: (06 ) 401775629 1/4/2019 | If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations a bradenhead test shall be performed. If the well was not sampled as part of a prior test it should be sampled if pressure is 25# or greater. If there is a need for sampling - contact COGCC engineering for verification of plugging procedures (Pressure greater than 25# or any liquids flowed to surface).
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling.
The Form 17 shall be submitted within 10 days of the test.
|
Engineer | Form: (06 ) 402385123 5/15/2020 | NOTE: Changes made to plugging procedure; CBL to be run prior to plugging to verify
existing coverage across lower and upper Arapahoe (CBL from 1200' to surface) -
submit to COGCC for verification of plugging orders. Additional plugs required.
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) For 1900’ plug: pump plug and displace - tag plug – must be 800’ or shallower. If
surface casing shoe plug (670’) not circulated to surface then tag plug – must be 300’ or
shallower and provide 10 sx plug at the surface (inside and outside of casing).
3) Properly abandon flowlines as per Rule 1105. File electronic Form 42 once
abandonment complete. Within 30 days of an operator completing abandonment
requirements for an off-location flowline or crude oil transfer line the operator must
submit a Flowline Report, Form 44. |
Engineer | Form: (06 ) 402385123 5/15/2020 | Operator shall implement measures to control venting, to protect health and safety, and
to ensure that vapors and odors from well plugging operations do not constitute a
nuisance or hazard to public welfare. |
Engineer | Form: (06 ) 402385123 5/15/2020 | If there has not been a reported Bradenhead test within 60 days of plugging this well,
prior to starting plugging operations a bradenhead test shall be performed. If the well
was not sampled as part of a prior test it should be sampled if pressure is 25# or
greater. If there is a need for sampling - contact COGCC engineering for verification of
plugging procedures (Pressure greater than 25# or any liquids flowed to surface).
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting
Instructions, Appendix A: Liquid and Gas Sampling.
The Form 17 shall be submitted within 10 days of the test. |