| Permit | Form: (02) 403810723 10/29/2025 | Operator will ensure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed. |
| Permit | Form: (02) 403810723 10/30/2025 | In the event delayed operations are to occur, Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017) |
| Engineer | Form: (02) 403810723 10/30/2025 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document Operator using Option 3. Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
PARRETT *1(API 123-05734)
NELSON *1(API 123-05747)
|
| Engineer | Form: (02) 403810723 10/30/2025 | Operator acknowledges the proximity of the listed wells. Operator assures that this offset list will be remediated per the Offset Well Evaluation and Hydraulic Fracturing Operator Guidance Document (option 4). Operator will submit a Form 42 (“OTHER- AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. The Form 42(s) shall be filed 48 hours prior to stimulation. No stimulation will occur within 750’ of the offset well bore(s). Stimulation occurring within 750-1500’ of any of the offset well bore(s) will have a 20% reduction in the treatment size(frac geometry) over the stages outside of the 1500’ radius. A statement shall be included on the Form 5A of the affected hz well(s) that documents the reduced and the excluded treatment intervals.
HALLETT *1(API 123-07350)
HALLETT *1(API 123-05736)
|
| Engineer | Form: (02) 403810723 10/30/2025 | Per Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact ECMC engineering for approval prior to stimulation.
2) If a delayed completion, a second test is required between 6-9 months after rig release and must be conducted prior to stimulation. If any pressure greater than 200 psi is observed or if there is continuous flow, Operator must contact ECMC engineering for approval prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance.
|
| Engineer | Form: (02) 403810723 10/30/2025 | 1) Submit Form 42 electronically to ECMC 2 business days prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 2 business day spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with a cement bond log.
|