SPILL OR RELEASE448719SPILL/RELEASE POINT
CHEVRON USA INC
16700
CL
9/23/2021
RANGELY
72370
RIO BLANCO  103
SENW 14 2N103W 6
314673View Related Related
 
Form 27/27AView Related Related View DocsDoc
Date Submitted:3/30/2021
Date Recv'd:3/30/2021Assigned by:Kris Neidel
DocNum:402643385Facility ID: 448719
Document Type:FORM 27 Project Number:19144
Operator Information:
Operator:SCOUT ENERGY MANAGEMENT LLC
Oper. No.10779
Address:13800 MONTFORT DRIVE SUITE 100  DALLAS  TX 75240
Type Of Facility:SPILL OR RELEASE
Fac. NameSPILL/RELEASE POINT
County Name:RIO BLANCO
Operator contact:Chris Patterson
qtrqtr: SENWsection: 14township: 2Nrange: 103Wmeridian: 6
Remediation Details:
Impacted Media
MediaImpactedExtentHow Determined?
SOILS Y2400ft. x 1ft. x 0.5 ft Field determined with tape measure
VEGETATION YMinor distressed vegetation noted. Visual
Reason for Report: SPILL
Cause of Condition: SPILL OR RELEASE
Potential Receptors: 
 
HOW REMEDIATE:  Subsequent soil samples analyzed for SAR at the SS4-SS7 sample locations and EC at the SS1-SS7 sample locations will be collected during 2021 to monitor natural attenuation. SAR and EC impacted soils will be treated in-situ by Natural Attenuation. After initial water wash seasonal precipitation events will be utilized.
 
INITIAL ACTION:  Internal corrosion on an injection line resulted in a release of approximately 89 bbls of produced water and no oil. Approximately 20 bbl of produced water was recovered. Additional information will be submitted on the supplemental report. The release is located approximately 10 feet east of the well (A.C. McLaughlin # 43). Fluids were removed with a vacuum truck and transported to the truck unloading facility at the Main Water Plant for recycling. The soil was water washed where produced water contacted the soil in the flow path. A soil sample location map and preliminary analytical results are included as an attachment.
 
RECLAMATION PLAN:  Site will be reclaimed and seeded once repairs are completed
 
SOURCE REMOVED:  No soil is intended for removal. Preliminary soil samples were collected on April 19, 2017 from the spill path. A total of nine (9) grab samples analyzed for Table 910-1 parameters were collected at a depths from 0 to 6 inches below ground surface (ft-bgs). Results show elevated SAR and EC levels within the impacted area. Subsequent soil samples analyzed for SAR at the SS4-SS7 sample locations and EC at the SS1-SS7 sample locations will be collected during 2021 to monitor natural attenuation. SAR and EC impacted soils will be treated in-situ by Natural Attenuation. After initial water wash seasonal precipitation events will be utilized.
 
Correspondence Log:
 
Coordinates:
TypeFacility IDFacility Name/NumLat/Long
Facility448719SPILL/RELEASE POINT
40.141475/-108.920888