Form 27/27A | Related Doc |
Date Submitted: | 3/30/2021 |
Date Recv'd: | 3/30/2021 | Assigned by: | Kris Neidel |
DocNum: | 402643385 | Facility ID: | 448719 |
Document Type: | FORM 27 | Project Number: | 19144 |
Operator Information: |
Operator: | SCOUT ENERGY MANAGEMENT LLC |
Oper. No. | 10779 |
Address: | 13800 MONTFORT DRIVE SUITE 100 DALLAS TX 75240 |
Type Of Facility: | SPILL OR RELEASE |
Fac. Name | SPILL/RELEASE POINT |
County Name: | RIO BLANCO |
Operator contact: | Cody Christian |
qtrqtr: SENW | section: 14 | township: 2N | range: 103W | meridian: 6 |
|
Remediation Details: |
|
Reason for Report: SPILL |
Cause of Condition: SPILL OR RELEASE |
Potential Receptors: |
|
HOW REMEDIATE: | Subsequent soil samples analyzed for SAR at the SS4-SS7 sample locations and EC at the SS1-SS7 sample locations will be collected during 2021 to monitor natural attenuation.
SAR and EC impacted soils will be treated in-situ by Natural Attenuation. After initial water wash seasonal precipitation events will be utilized.
|
|
INITIAL ACTION: | Internal corrosion on an injection line resulted in a release of approximately 89 bbls of produced water and no oil. Approximately 20 bbl of produced water was recovered. Additional information will be submitted on the supplemental report. The release is located approximately 10 feet east of the well (A.C. McLaughlin # 43). Fluids were removed with a vacuum truck and transported to the truck unloading facility at the Main Water Plant for recycling. The soil was water washed where produced water contacted the soil in the flow path. A soil sample location map and preliminary analytical results are included as an attachment. |
|
RECLAMATION PLAN: | Site will be reclaimed and seeded once repairs are completed |
|
SOURCE REMOVED: | No soil is intended for removal. Preliminary soil samples were collected on April 19, 2017 from the spill path. A total of nine (9) grab samples analyzed for Table 910-1 parameters were collected at a depths from 0 to 6 inches below ground surface (ft-bgs). Results show elevated SAR and EC levels within the impacted area.
Subsequent soil samples analyzed for SAR at the SS4-SS7 sample locations and EC at the SS1-SS7 sample locations will be collected during 2021 to monitor natural attenuation.
SAR and EC impacted soils will be treated in-situ by Natural Attenuation. After initial water wash seasonal precipitation events will be utilized.
|
|
Correspondence Log: |
|
Coordinates: |
Type | Facility ID | Facility Name/Num | Lat/Long |
Facility | 448719 | SPILL/RELEASE POINT | 40.141475/-108.920888 |
|