SPILL OR RELEASE450198Fee 60 Injection Line
1
CHEVRON USA INC
16700
CL
9/23/2021
RANGELY
72370
RIO BLANCO  103
SWNE 28 2N102W 6
311801View Related Related
 
Form 27/27AView Related Related View DocsDoc
Date Submitted:3/30/2021
Date Recv'd:3/30/2021Assigned by:Kris Neidel
DocNum:402643191Facility ID: 450198
Document Type:FORM 27 Project Number:18600
Operator Information:
Operator:SCOUT ENERGY MANAGEMENT LLC
Oper. No.10779
Address:13800 MONTFORT DRIVE SUITE 100  DALLAS  TX 75240
Type Of Facility:SPILL OR RELEASE
Fac. NameFee 60 Injection Line
County Name:RIO BLANCO
Operator contact:Chris Patterson
qtrqtr: SWNEsection: 28township: 2Nrange: 102Wmeridian: 6
Remediation Details:
Impacted Media
MediaImpactedExtentHow Determined?
SOILS Y1026ft. x 2ft. x 0.5 ft Field determined with tape measure
Reason for Report: SPILL
Cause of Condition: SPILL OR RELEASE
Potential Receptors: 
 
HOW REMEDIATE:  At this time no soil is intended for removal, however if the DRO level remains above Table 910-1 standards then impacted soil around the SS1 location will likely be removed. SAR and EC impacted soils will be treated in-situ by Natural Attenuation. After initial water wash seasonal precipitation events will be utilized. Subsequent soil samples analyzed for SAR and EC at SS1-SS7 sample locations as well as for DRO at SS1 sample location will be collected during 2021 to monitor natural attenuation. The DRO resample at SS1 is intended to give a current representation of DRO levels in this area. Due to lack of noted stained soil during initial sampling event it is not believed that hydrocarbon impacts were widespread.
 
INITIAL ACTION:  On Sunday April 16, 2017 we had a release of 120 bbls injection water from the injection line at the Fee 60. No visible oil was released. We recovered 30 bbls of injection water. The area will be water washed and samples will be taken to ensure compliance with table 910-1. A soil sample location map and preliminary analytical results are included as an attachment.
 
RECLAMATION PLAN:  Site was reclaimed and seeded once repairs are completed.
 
SOURCE REMOVED:  At this time no soil is intended for removal, however if the DRO level remains above Table 910-1 standards then impacted soil around the SS1 location will likely be removed. SAR and EC impacted soils will be treated in-situ by Natural Attenuation. After initial water wash seasonal precipitation events will be utilized. Subsequent soil samples analyzed for SAR and EC at SS1-SS7 sample locations as well as for DRO at SS1 sample location will be collected during 2021 to monitor natural attenuation. The DRO resample at SS1 is intended to give a current representation of DRO levels in this area. Due to lack of noted stained soil during initial sampling event it is not believed that hydrocarbon impacts were widespread.
 
Correspondence Log:
 
Coordinates:
TypeFacility IDFacility Name/NumLat/Long
Facility450198Fee 60 Injection Line
1
40.115658/-108.841194