Click for Specifics | Full | 5/17/2024 | 5/30/2024 | | 0 | Down to Zero | -- | 0 | Down to Zero | 294 | 293 | No | No | No | Annual Test. 0 PSI, with no pressure or flow observed for the entire 30-minute test. PDC will monitor pressure and re-test according to bradenhead policy. |
Click for Specifics | Full | 5/1/2023 | 5/8/2023 | | 3 | Down to Zero | -- | 0 | No Flow | 293 | 312 | No | None | None | Annual Test. 3 PSI blew down to 0 PSI within first few seconds of test. No pressure or flow observed for the remainder of the test. PDC will monitor pressure and re-test according to bradenhead policy. |
Click for Specifics | Full | 5/25/2022 | 6/13/2022 | | 0 | No Flow | -- | 0 | No Flow | 308 | 306 | No | None | None | |
Click for Specifics | Full | 9/18/2021 | 11/1/2021 | | 0 | No Flow | -- | 0 | No Flow | 390 | 393 | No | None | None | |
402425176 | Form 17 | 2/14/2020 | 6/17/2020 | | 3 | DOWN TO 0 | -- | 0 | NO FLOW | 531 | 532 | No | -- | -- | 6 month follow-up test post abatement system install. PDC will continue to monitor pressure and report any increase in pressure to COGCC. |
402114644 | Form 17 | 6/30/2019 | 7/18/2019 | FLOWING | 54 | DOWN TO 0 | -- | 0 | NO FLOW | 720 | 720 | No | -- | -- | Annual Test 54 PSI blew down to 0 PSI instantly, no pressure or flow observed for the remainder of the 30 min test. PDC has submitted a remediation plan via sundry |
401440767 | Form 17 | 10/15/2017 | 10/25/2017 | FLOWING | 760 | DOWN TO 0 | -- | 0 | NO FLOW | 2393 | 2393 | Yes | Yes | -- | Post Production Test, blew down to zero within 30 seconds. Gas Sample Collected. Requested 14 day blowdown period |
401347670 | Form 17 | 7/14/2017 | 7/19/2017 | SHUT-IN | 725 | DOWN TO 0 | -- | 0 | NO FLOW | 0 | 0 | No | -- | -- | Pre Completion Test initial pressure 725 PSI BLEED TO 0 PSI WITHIN seconds no flow for duration of test |
401327803 | Form 17 | 5/15/2017 | 6/29/2017 | SHUT-IN | 650 | DOWN TO 0 | -- | 0 | NO FLOW | 0 | 0 | No | -- | -- | Pre Completion test. Initial pressure was 650 PSI, instantly blew down within first minute of test to 0 PSI. No pressure for remainder of test. Attempted to collect sample but were unable to due instant blow down. |