WELL05-123-24854BRENT
1-6I
PDC ENERGY INC
69175
PA
12/17/2025
WATTENBERG
90750
WELD  123
SENW 20 5N64W 6
332822
   
Search for Different Bradenhead:
County Code: Sequence Code:
 
Surface Casing Depth: 588 ft.
View Form/DetailsReport TypeTest DateSubmit DateWell StatusInitial Surf CasingBradenhead Flow (Start)Fluid TypeEnd Surf CasingBradenhead Flow (End)Initial Prod CasingEnd Prod CasingSample Taken?GasLiquidComments
404403795Form 1710/9/202510/24/2025SHUT-IN41DOWN TO 0 GAS0 NO FLOW 00No----Pre-P&A. 41 PSI blew down to 0 PSI within first few seconds of test. No pressure or flow observed for the remainder of the test.
404380172Form 179/18/202510/6/2025SHUT-IN45DOWN TO 0 GAS0 NO FLOW 00No----Remediation follow up test. 45 PS blew down to 0 PSI within first few seconds of test. No pressure or flow observed for the remainder of the test. Operator will monitor pressure and re-test according to bradenhead policy.
404104854Form 172/10/20252/24/2025SHUT-IN15DOWN TO 0 GAS0 WHISPER 542542No----Pre-P&A. 15 PSI blew down to 0 PSI within first few seconds of test, very low whisper for remainder of the test.
Click for SpecificsFull1/9/20251/28/2025 18Down to Zero--0No Flow00NoNoNoAnnual Test.  18 PSI blew down to 0 PSI within first few seconds of test.  No pressure or flow observed for the remainder of the test. PDC will monitor pressure and re-test according to bradenhead policy.
Click for SpecificsFull3/1/20243/19/2024Shut In16Down to Zero--0Down to Zero360360NoNoNoAnnual Test. 16 PSI blew down to 0 PSI within first few seconds of test. No pressure or flow observed for the remainder of the test. PDC will monitor pressure and re-test according to bradenhead policy.
Click for SpecificsFull1/12/20231/30/2023 10Down to Zero--0Down to Zero370370NoNoneNoneAnnual Test. 10 PSI blew down to 0 PSI within first few seconds of test. No pressure or flow observed for the remainder of the test. PDC will continue to monitor monthly.
403203200Form 1710/19/202210/20/2022SHUT-IN7DOWN TO 0 GAS0 NO FLOW 420420No----Abatement system follow up test. 7 PSI gas flow blew down to 0 PSI within first few seconds of test. No pressure or flow observed for the remainder of the test. PDC will submit sundry with bradenhead details as soon as possible. PDC will continue to monitor monthly.
403018693Form 174/17/20224/18/2022SHUT-IN70CONTINUOUS GAS0 NO FLOW 426426Yes----Monthly Gauge High Pressure Follow-Up, 70 PSI gas flow blew down to 0 PSI within first 10 minutes of test. No pressure or flow observed for the remainder of the test. PDC will schedule a sampling event and submit results via form 43 as well as a remediation plan via sundry as soon as possible. PDC will continue to monitor monthly.
Click for SpecificsFull10/30/202111/22/2021 2Down to Zero--0No Flow281298NoNoneNone 
Click for SpecificsLight10/18/202012/3/2020 0 --0No Flow362362NoNoNo 
Click for SpecificsLight7/22/20198/18/2020 25 --0 362362NoNoNo