| Click for Specifics | Full | 2/24/2025 | 3/11/2025 | | 327 | N/A | -- | 0 | No Flow | 381 | 372 | No | No | No | TEP Rocky Mountain LLC (TEP) has received ECMC approval to not test the intermediate casing annulus due to safety concerns associated with the testing process. 2" Blowdown Cycled during test |
| Click for Specifics | Full | 8/7/2024 | 9/4/2024 | | 88 | N/A | -- | 0 | No Flow | 243 | 229 | No | No | No | TEP Rocky Mountain LLC (TEP) has received ECMC approval to not test the intermediate casing annulus due to safety concerns associated with the testing process. BH 2" valve |
| Click for Specifics | Full | 2/20/2023 | 3/15/2023 | Flowing | 291 | N/A | -- | 0 | No Flow | 584 | 586 | No | No | No | 1/2 valve |
| Click for Specifics | Full | 2/24/2022 | 3/7/2022 | Clock/Intermitter | 181 | N/A | -- | 0 | No Flow | 515 | 514 | No | No | No | 1/2 valve |
| Click for Specifics | Full | 7/7/2021 | 8/9/2021 | Flowing | 240 | N/A | -- | 0 | No Flow | 285 | 285 | No | No | No | |