| 404545662 | Form 17 | 2/4/2026 | 2/13/2026 | CLOCK/INTERMITTER | 88 | CONTINUOUS | GAS | 0 | NO FLOW | 33 | 35 | No | -- | -- | This is an annual bradenhead test that was performed after a seven-day shut-in period. This well has an approved pressure management plan. The test was performed through a 2 inch valve. Intermediate test performed through 1/2" valve. |
| 404175749 | Form 17 | 4/23/2025 | 4/23/2025 | CLOCK/INTERMITTER | 103 | CONTINUOUS | GAS | 0 | WHISPER | 36 | 38 | No | -- | -- | This is an annual bradenhead test that was performed after a seven-day shut-in period. The bradenhead is connected to the flow line with an approved pressure management plan. The bradenhead test was performed through a 2 inch valve. Intermediate test was performed through a 1/2 inch valve. |
| 403872382 | Form 17 | 7/29/2024 | 7/31/2024 | CLOCK/INTERMITTER | 132 | CONTINUOUS | GAS | 0 | WHISPER | 47 | 38 | No | -- | -- | This is an annual bradenhead test that was performed after a seven-day shut-in period. The bradenhead is connected to the flow line with an approved pressure management plan. The test was performed through a 2 inch valve. Intermediate test was performed through a 1/2 inch valve. |
| 403495073 | Form 17 | 8/11/2023 | 8/14/2023 | CLOCK/INTERMITTER | 428 | CONTINUOUS | GAS | 2 | CONTINUOUS | 43 | 43 | No | -- | -- | TEP staff identified this well as a three string well and that the previous operator had inadvertently connected the intermediate casing to the flowline instead of the bradenhead. Staff excavated around the wellhead and located the buried bradenhead valve. The bradenhead was tested through a 2" valve and the intermediate casing was tested through a 1/2" valve. |
| Click for Specifics | Full | 2/22/2022 | 3/7/2022 | Plunger Lift | 51 | N/A | -- | 51 | N/A | 251 | 257 | No | No | No | tied in |
| Click for Specifics | Full | 6/29/2021 | 7/12/2021 | Shut-In | 73 | N/A | -- | 73 | N/A | 265 | 265 | No | No | No | bradenhead is tied into tubing and selling. |
| 402413698 | Form 17 | 6/3/2020 | 6/4/2020 | PLUNGER LIFT | 158 | GAS | -- | 0 | VAPOR | 218 | 227 | No | -- | -- | Bradenhead left open and added to flow test list per Craig Burger. |
| Click for Specifics | Light | 6/19/2019 | 6/2/2020 | | 2 | | | 0 | | -- | -- | No | No | No | |
| Click for Specifics | Light | 6/13/2017 | 6/2/2020 | | 0 | | | 0 | | -- | -- | No | No | No | |
| Click for Specifics | Light | 6/22/2016 | 6/2/2020 | | 5 | | | 0 | | -- | -- | No | No | No | |