WELL05-001-09891Kortum LD
33-165HN
PDC ENERGY INC
69175
PR
10/1/2024
WATTENBERG
90750
ADAMS  001
NWNE 21 1S67W 6
443415
   
Search for Different Bradenhead:
County Code: Sequence Code:
 
Surface Casing Depth: 2037 ft.
View Form/DetailsReport TypeTest DateSubmit DateWell StatusInitial Surf CasingBradenhead Flow (Start)Fluid TypeEnd Surf CasingBradenhead Flow (End)Initial Prod CasingEnd Prod CasingSample Taken?GasLiquidComments
Click for SpecificsFull11/17/202511/24/2025 0No Flow--0No Flow400400NoNoNoAnnual Test.  0 PSI, with no pressure or flow observed for the entire 30-minute test.  Operator will monitor pressure and re-test according to bradenhead policy.
404196794Form 174/22/20255/8/2025GAS LIFT1CONTINUOUS GAS1 WHISPER 456456No----Remediation follow up test. 1 PSI continuous gas flow, did not blow down. Whisper gas continued for entire test. Operator will monitor pressure and re-test according to bradenhead policy.
Click for SpecificsFull4/26/20244/30/2024 0Down to Zero--0Down to Zero684684NoNoNo 
403354191Form 173/22/20233/23/2023FLOWING19DOWN TO 0 WATER AND GAS0 DOWN TO 0 23242322No----Post-Production within 60 days of first sales. 19 PSI water and gas flow blew down to 0 PSI within first minute of test, water continued dripping for the remainder of the test. PDC will monitor bradenhead pressure monthly and submit annual test.
403352239Form 173/17/20233/21/2023FLOWING245DOWN TO 0 WATER AND GAS0 NO FLOW 24682467YesYes--Post-Production within 30 days of first sales. 245 PSI gas on open for ~1 second and cut to water. Produced ~3 gallons of water and died. No flow for remainder of test. PDC will monitor bradenhead pressure monthly and submit annual test.
403131132Form 178/9/20228/10/2022SHUT-IN0NO FLOW --0 NO FLOW 00No----Delayed Completions Test. 0 PSI, no pressure or flow observed for the entire test.
403095605Form 177/1/20227/5/2022SHUT-IN0NO FLOW --0 NO FLOW 00No----Initial Test Post Rig Release. 0 PSI, no pressure or flow observed for the entire 30 min test. PDC will monitor pressure and re-test according to bradenhead policy.