Click image to view related facilities. Related  Click image to view inspection information. InspClick image to view MIT information. MITGIS Map GISClick image to view imaged documents for this well/facility. DocClick image to view imaged documents for this well/facility. COAClick image to view wellbore completion diagram. WellboreClick image to search for orders within this facility's section. OrdersClick image to view bradenhead scoutcard data. Bradenhead
 Surface Location
 API# 05-123-36860
Well Classification: OW Status: SI - 6/1/2024
Well Name/No:Boyd #3-19
(Click Well Name for Production Data)
Click Here for Transporter Gatherer Info
Operator:CRESTONE PEAK RESOURCES OPERATING LLC - 10633
(Click Operator Name for Company Detail Report)
Federal Or State Lease #:
Facility Status:SIStatus Date6/1/2024
FacilityID:431914LocationID:431916
County:WELD #123Location:SESW 19 3N68W 6
Field:WATTENBERG - #90750Elevation:5019 ft.
Basin:DENVER (DJ) BASIN  
Planned Location:1163FSL  1406 FWLLat/Long: 40.206870 / -105.050140Lat/Long Source: Field Measured
As Drilled Location:Footages Not AvailableLat/Long: 40.206883 / -105.050138Lat/Long Source: Field Measured
 
FracFocus
Disclosure: Sidetrack #00
Start Date: 8/24/2013
End Date: 8/24/2013
Reported: 10/21/2013
Days to report: 58
 Wellbore And Formation Details -- select either a wellbore Or formation to expand.
 

Wellbore #00             Wellbore Classification: GW             Status: SI - 6/1/2024             Measured TD: 7637 ft.    Vertical TD: 7625 ft.

 Wellbore Data for Original WellboreWellbore Classification: GW        SI - 6/1/2024
Wellbore PermitDIRECTIONAL
Permit #: Expiration Date:2/21/2015
Proposed Top PZ Location:Sec:19 Twp: 3N 68W Footage: 1033 FSL  1480 FWL
Bottom Hole Location:Sec:19 Twp: 3N 68W Footage: 1015 FSL  1573 FWL
Proposed Depth/Form:7500 ft.
Surface Mineral Owner Same:Yes
Mineral Owner:FEESurface Owner:FEE
Unit: Unit Number:
Formation And Spacing:Code: CODL , Formation: CODELL , Order: 407 , Unit Acreage: 160, Drill Unit: SW/4
Formation And Spacing:Code: JSND , Formation: J SAND , Order: 232 , Unit Acreage: 320, Drill Unit: S/2
Formation And Spacing:Code: NBRR , Formation: NIOBRARA , Order: 407 , Unit Acreage: 160, Drill Unit: SW/4
Casing:String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: 0 ft., Depth: 450 ft., Weight: 24 , Citings Type: PLANNED
Cement:Sacks: 180, Top: 0 ft., Bottom: 450 ft.
Casing:String Type: 1ST, Hole Size: 7.875 in., Size: 4.5 in., Top: 0 ft., Depth: 7500 ft., Weight: 11.6 , Citings Type: PLANNED
Cement:Sacks: 170, Top: 6440 ft., Bottom: 7500 ft.

Wellbore Completed
Completion Date:5/5/2013
Spud Date:4/30/2013Spud Date Is:ACTUAL
Measured TD:7637 ft.Measured PB depth:7590 ft.
True Vertical TD:7625 ft.True Vertical PB depth:7578 ft.
Top PZ Location:Sec:19 Twp: 3N 68WFootage: 1033 FSL  1480 FWL
Bottom Hole Location:Sec:19 Twp: 3N 68WFootage: 1015 FSL  1573 FWL
Log Types:Cement Bond Log, V.D.L. Gamma-Ray & C.C.L High Resolution Induction, Compensated Density, Compensated Neutron BHC Sonic, Gamma Ray, Caliper
Log Types:CBL, IND/DENS/NEU, SONIC
Casing:String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: 0 ft., Depth: 633 ft., Weight: 24 , Citings Type: ACTUAL
Cement:Sacks: 245, Top: 0 ft., Bottom: 633 ft., Determination Method: VISU
Casing:String Type: 1ST, Hole Size: 7.875 in., Size: 4.5 in., Top: 0 ft., Depth: 7614 ft., Weight: 11.6 , Citings Type: ACTUAL
Cement:Sacks: 690, Top: 2414 ft., Bottom: 7614 ft., Determination Method: CBL
FormationInterval TopLog BottomCoredDSTs
SUSSEX3671 ft.
NIOBRARA6754 ft.
FORT HAYS7016 ft.
CODELL7039 ft.
J SAND7479 ft.

Formation JSND                     Formation Classification:  OW                     Status:  SI - 6/1/2024                  Interval Top: 7493 ft.    Interval Bottom: 7521 ft.

 Completed Information for Formation J SAND
1st Production Date:11/1/2013Choke Size: 
Formation Name:J SANDCommingled:Yes
Production Method:
Open Hole Completion:
Formation Treatment
Treatment Type:FRACTURE STIMULATION
Treatment Date:8/24/2013Treatment End Date:8/24/2013
Treatment Summary:FRAC JSND WITH 4103 BBLS OF SLICKWATER, 4103 BBLS TOTAL FLUID, 150040 POUNDS OF SAND.
Total fluid used in treatment (bbls):4103Max pressure during treatment (psi):4151
Total gas used in treatment (mcf):Fluid density (lbs/gal):8.30
Type Of gas:Number Of staged intervals:1
Total acid used in treatment (bbls):Min frac gradient (psi/ft):0.89
Recycled water used in treatment (bbls):Total flowback volume recovered (bbls):1325
Fresh water used in treatment (bbls):Disposition method For flowback:DISPOSAL
Total proppant used (lbs):150040Green completions techniques utilized:Yes
Reason green techniques Not utilized: 
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation JSND.
Perforation Data:
Interval Top:7493 ft.# Of Holes:63
Interval Bottom:7521 ft.Hole Size:0.42 in.

Formation CODL                     Formation Classification:  OW                     Status:  CM - 2/7/2014                  Interval Top: 7040 ft.    Interval Bottom: 7061 ft.

 Completed Information for Formation CODELL
1st Production Date:11/1/2013Choke Size: 
Formation Name:CODELLCommingled:Yes
Production Method:
Open Hole Completion:
Formation Treatment
Treatment Type:FRACTURE STIMULATION
Treatment Date:8/24/2013Treatment End Date:8/24/2013
Treatment Summary:FRAC CODL WITH 4401 BBLS OF SLICKWATER, 4401 BBLS TOTAL FLUID, 150,000 POUNDS OF SAND.
Total fluid used in treatment (bbls):4401Max pressure during treatment (psi):4151
Total gas used in treatment (mcf):Fluid density (lbs/gal):8.30
Type Of gas:Number Of staged intervals:1
Total acid used in treatment (bbls):Min frac gradient (psi/ft):0.89
Recycled water used in treatment (bbls):Total flowback volume recovered (bbls):1325
Fresh water used in treatment (bbls):Disposition method For flowback:DISPOSAL
Total proppant used (lbs):150000Green completions techniques utilized:Yes
Reason green techniques Not utilized: 
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation CODL.
Perforation Data:
Interval Top:7040 ft.# Of Holes:63
Interval Bottom:7061 ft.Hole Size:0.42 in.

Formation JNBCD                   Formation Classification:  OW                   Status:  CM - 11/14/2013                Interval Top: 6829 ft.    Interval Bottom: 7521 ft.

 Completed Information for Formation J-NIOBRARA-CODELL
1st Production Date:11/1/2013Choke Size: 
Formation Name:J-NIOBRARA-CODELLCommingled:No
Production Method:
Open Hole Completion:
Tubing Size:2.375 in.Tubing Setting Depth:7463 ft.
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
Initial Test Data:
Test Date:11/14/2013Test Method:
Hours Tested:24Gas Type:DRY
Gas Disposal:SOLD
Test TypeMeasure
BBLS_H2O 10
BBLS_OIL 71
BTU_GAS 1245
CALC_BBLS_H2O 10
CALC_BBLS_OIL 71
CALC_GOR 1084
CALC_MCF_GAS 77
CASING_PRESS 1707
GRAVITY_OIL 45
MCF_GAS 77
TUBING_PRESS 1655
Perforation Data:
Interval Top:6829 ft.# Of Holes:230
Interval Bottom:7521 ft.Hole Size:0.42 in.

Formation NB-CD                   Formation Classification:  OW                   Status:  SI - 6/1/2024                  Interval Top: 6829 ft.    Interval Bottom: 7061 ft.

 Completed Information for Formation NIOBRARA-CODELL
1st Production Date:11/1/2013Choke Size: 
Formation Name:NIOBRARA-CODELLCommingled:Yes
Production Method:
Open Hole Completion:
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation NB-CD.
Perforation Data:
Interval Top:6829 ft.# Of Holes:167
Interval Bottom:7061 ft.Hole Size:0.42 in.

Formation NBRR                     Formation Classification:  OW                     Status:  CM - 2/7/2014                  Interval Top: 6829 ft.    Interval Bottom: 6924 ft.

 Completed Information for Formation NIOBRARA
1st Production Date:11/1/2013Choke Size: 
Formation Name:NIOBRARACommingled:Yes
Production Method:
Open Hole Completion:
Formation Treatment
Treatment Type:FRACTURE STIMULATION
Treatment Date:8/24/2013Treatment End Date:8/24/2013
Treatment Summary:FRAC NBRR WITH 12 BBLS ACID, 4401 BBLS SLICKWATER, 4413 BBLS TOTAL FLUID, 150000 POUNDS OF SAND.
Total fluid used in treatment (bbls):4413Max pressure during treatment (psi):4901
Total gas used in treatment (mcf):Fluid density (lbs/gal):8.30
Type Of gas:Number Of staged intervals:1
Total acid used in treatment (bbls):12Min frac gradient (psi/ft):0.90
Recycled water used in treatment (bbls):Total flowback volume recovered (bbls):7463
Fresh water used in treatment (bbls):Disposition method For flowback:DISPOSAL
Total proppant used (lbs):150000Green completions techniques utilized:Yes
Reason green techniques Not utilized: 
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation NBRR.
Perforation Data:
Interval Top:6829 ft.# Of Holes:104
Interval Bottom:6924 ft.Hole Size:0.42 in.
Primary Well Designation:
Out Of Service      i
            All DesignationsDate
Reported PluggedN 
Out Of Service RepurposedN 
Out Of ServiceYPlugging Due Date
08/26/2028
Inactive ExceptionN 
Noticed InactiveN 
Defined Inactive (SI )YDefined Inactive
05/31/2024
Low ProducingYProduction Period
12/2024 - 11/2025

BOE/MCFE/GOR Calculations
Production for Previous 12 Months
December 2024 - November 2025i
Total Oil Produced (Barrels)0
Total Gas Produced (MCF)0
GOR
GOR Determination 
Average BOE per Day0.000
Average MCFE per Day0.000

 Federal Financial Assurance  i 

 Tribal Well  i No