Skip to Main Content

COGIS

Facility Detail

COGIS - WELL SCOUT CARD

Click image to view related facilities. Related  Click image to view inspection information. InspClick image to view MIT information. MITGIS Map GISOld GIS Map Old GISClick image to view imaged documents for this well/facility. DocClick image to view imaged documents for this well/facility. COAClick image to view wellbore completion diagram. WellboreClick image to search for orders within this facility's section. OrdersClick image to view bradenhead scoutcard data. Bradenhead
 Surface Location
 API# 05-123-32471
Well Classification: GW Status: PA - 7/25/2025
Well Name/No:WANDELL #8-2-7
(Click Well Name for Production Data)
Click Here for Transporter Gatherer Info
Operator:CRESTONE PEAK RESOURCES OPERATING LLC - 10633
(Click Operator Name for Company Detail Report)
Federal Or State Lease #:
Facility Status:PAStatus Date7/25/2025
FacilityID:420132LocationID:336439
Municipality/County:FIRESTONE / WELD #123Location:NENE 7 2N67W 6
Field:WATTENBERG - #90750Elevation:4892 ft.
Basin:DENVER (DJ) BASIN  
Planned Location:925FNL  1135 FELLat/Long: 40.157860 / -104.927860Lat/Long Source: Field Measured
As Drilled Location:Footages Not AvailableLat/Long: 40.157895 / -104.927840Lat/Long Source: Field Measured
 
FracFocus
Disclosure: Sidetrack #00
Start Date: 4/7/2011
End Date: 4/7/2011
Reported: 2/1/2012
Prior to rule 205A.b.(2)(A)
Days to report: 300
 Wellbore And Formation Details -- select either a wellbore Or formation to expand.
 

Wellbore #00             Wellbore Classification: GW             Status: AB - 7/25/2025             Measured TD: 8111 ft.    Vertical TD: 7952 ft.

 Wellbore Data for Original WellboreWellbore Classification: GW        AB - 7/25/2025
Wellbore PermitDIRECTIONAL
Permit #: Expiration Date:10/29/2012
Proposed Top PZ Location:Sec:7 Twp: 2N 67W Footage: 1350 FNL  50 FEL
Bottom Hole Location:Sec:7 Twp: 2N 67W Footage: 1350 FNL  50 FEL
Proposed Depth/Form:8082 ft.
Surface Mineral Owner Same:No
Mineral Owner:FEESurface Owner:FEE
Unit: Unit Number:
Formation And Spacing:Code: CODL , Formation: CODELL , Order: 407 , Unit Acreage: 160, Drill Unit: GWA
Formation And Spacing:Code: JSND , Formation: J SAND , Order: 232 , Unit Acreage: 160, Drill Unit: GWA
Formation And Spacing:Code: NBRR , Formation: NIOBRARA , Order: 407 , Unit Acreage: 160, Drill Unit: GWA
Casing:String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: , Depth: 450 ft., Weight: 24 , Citings Type: PLANNED
Cement:Sacks: 200, Top: 0 ft., Bottom: 450 ft.
Casing:String Type: 1ST, Hole Size: 7.875 in., Size: 4.5 in., Top: , Depth: 8082 ft., Weight: 11.6 , Citings Type: PLANNED
Cement:Sacks: 270, Top: 7043 ft., Bottom: 8082 ft.

Wellbore Completed
Completion Date:3/19/2011
Spud Date:3/14/2011Spud Date Is:ACTUAL
Measured TD:8111 ft.Measured PB depth:8056 ft.
True Vertical TD:7952 ft.True Vertical PB depth:7897 ft.
Top PZ Location:Sec:7 Twp: 2N 67WFootage: 454 FNL  74 FEL
Bottom Hole Location:Sec:7 Twp: 2N 67WFootage: 457 FNL  81 FEL
Log Types:CBL, DUAL IND/COMPENSATED DENSITY/COMPENSATED NEUTRON
Casing:String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: 0 ft., Depth: 939 ft., Weight: 32 , Citings Type: ACTUAL
Cement:Sacks: 376, Top: 0 ft., Bottom: 939 ft., Determination Method: VISU
Casing:String Type: 1ST, Hole Size: 7.875 in., Size: 4.5 in., Top: 0 ft., Depth: 8097 ft., Weight: 11.6 , Citings Type: ACTUAL
Cement:Sacks: 710, Top: 3126 ft., Bottom: 8097 ft., Determination Method: CBL
FormationInterval TopLog BottomCoredDSTs
SUSSEX4346 ft.
NIOBRARA7296 ft.
CODELL7548 ft.
J SAND7978 ft.

Formation JSND                     Formation Classification:  GW                     Status:  AB - 7/25/2025                 Interval Top: 7978 ft.    Interval Bottom: 8012 ft.

 Completed Information for Formation J SAND
1st Production Date:N/AChoke Size: 
Formation Name:J SANDCommingled:No
Production Method:
Open Hole Completion:No
Formation Treatment
Treatment Date:4/7/2011
Treatment Summary:J SAND COMPLETION. FRAC'D THE J-SAND 7978'-7992', 8000'-8012' (52 HOLES) W/155,106 GAL 19 # PHASERFRAC HYBRID CROSS LINKED GEL CONTAINING 251,060 # 20/40 SAND. 04/07/2011.
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation JSND.
Perforation Data:
Interval Top:7978 ft.# Of Holes:52
Interval Bottom:8012 ft.Hole Size:0.42 in.

Formation CODL                     Formation Classification:  GW                     Status:  CM - 4/15/2025                 Interval Top: 7548 ft.    Interval Bottom: 7568 ft.

 Completed Information for Formation CODELL
1st Production Date:N/AChoke Size: 
Formation Name:CODELLCommingled:Yes
Production Method:
Open Hole Completion:No
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation CODL.
Perforation Data:
Interval Top:7548 ft.# Of Holes:40
Interval Bottom:7568 ft.Hole Size:0.42 in.

Formation JNBCD                   Formation Classification:  GW                   Status:  CM - 7/5/2011                  Interval Top: 7332 ft.    Interval Bottom: 8012 ft.

 Completed Information for Formation J-NIOBRARA-CODELL
1st Production Date:N/AChoke Size: 
Formation Name:J-NIOBRARA-CODELLCommingled:
Production Method:
Open Hole Completion:
Formation Treatment
Treatment Date:6/12/2011
Treatment Summary:JSND-CDL-NBRR COMMINGLE. SET CBP @ 04/30/11. DRILLED OUT CBP @ 80'. 05/04/11. DRILLED OUT CFP @ 7430'. 05/04/11. DRILLED OUT CFP @ 7640' TO COMMINGLE THE JSND-CDL-NBRR 05/05/11.
Formation Treatment
Treatment Date:5/7/2011
Treatment Summary:JSND-CDEL-NBRR COMMINGLE. SET CBP @ 80'. 04/30/2011. DRILLED OUT CBP @ 80'. 05/04/11. DRILLED OUT CFP @ 7430'. 05/04/2011. DRILLED OUT CFP @ 7640' TO COMMINGLE THE JSND-CDL-NBRR 05/05/2011.
Tubing Size:2.375 in.Tubing Setting Depth:7957 ft.
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
Initial Test Data:
Test Date:6/12/2011Test Method:FLOWING
Hours Tested:24Gas Type:DRY
Gas Disposal:SOLD
Test TypeMeasure
BBLS_H2O 18
BBLS_OIL 24
BTU_GAS 1271
CALC_BBLS_H2O 16
CALC_BBLS_OIL 24
CALC_GOR 13000
CALC_MCF_GAS 312
CASING_PRESS 1022
GRAVITY_OIL 50
MCF_GAS 312
TUBING_PRESS 247
Perforation Data:
Interval Top:7332 ft.# Of Holes:172
Interval Bottom:8012 ft.Hole Size:

Formation NB-CD                   Formation Classification:  GW                   Status:  AB - 7/25/2025                 Interval Top: 7332 ft.    Interval Bottom: 7568 ft.

 Completed Information for Formation NIOBRARA-CODELL
1st Production Date:N/AChoke Size: 
Formation Name:NIOBRARA-CODELLCommingled:No
Production Method:
Open Hole Completion:No
Formation Treatment
Treatment Date:4/7/2011
Treatment Summary:CDL-NBRR COMPLETION. SET CFP @ 7640'. 04/07/2011. FRAC'D THE CODELL 7548'-7568' (40 HOLES) W/109,578 GAL 22 # PHASERFRAC HYBRID CROSS LINKED GEL CONTAINING 251,420 # 20/40 SAND. 04/07/2011. SET CFP @ 7430'. 04/07/2011. FRAC'D THE NIOBRARA 7332'-7352' (80 HOLES) W/135,240 GALS 18 # PHASERFRAC HYBRID CROSS LINKED GEL CONTAINING 250,700 # 20/40 SAND. 04/07/2011.
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation NB-CD.
Perforation Data:
Interval Top:7332 ft.# Of Holes:120
Interval Bottom:7568 ft.Hole Size:

Formation NBRR                     Formation Classification:  GW                     Status:  CM - 4/15/2025                 Interval Top: 7332 ft.    Interval Bottom: 7352 ft.

 Completed Information for Formation NIOBRARA
1st Production Date:N/AChoke Size: 
Formation Name:NIOBRARACommingled:Yes
Production Method:
Open Hole Completion:No
Tubing Size:Tubing Setting Depth:
Tubing Packer Depth:Tubing Multiple Packer:
Open Hole Top:Open Hole Bottom:
No Initial Test Data was found for formation NBRR.
Perforation Data:
Interval Top:7332 ft.# Of Holes:80
Interval Bottom:7352 ft.Hole Size:0.7 in.
Primary Well Designation:
None      i
            All DesignationsDate
Reported PluggedY07/25/2025
Out Of Service RepurposedN 
Out Of ServiceYPlugging Due Date
12/31/2030
Inactive ExceptionN 
Noticed InactiveN 
Defined InactiveN 
Low ProducingN 

BOE/MCFE/GOR Calculations
Production for Previous 12 Months
December 2024 - November 2025i
Total Oil Produced (Barrels)0
Total Gas Produced (MCF)0
GOR
GOR DeterminationMCFE
Average BOE per Day0.000
Average MCFE per Day0.000

 Federal Financial Assurance  i 

 Tribal Well  i No