Wellbore #00 Wellbore Classification: GW Status: AB - 8/28/2024 Measured TD: 8383 ft. Vertical TD: 8120 ft.| Wellbore Data for Original Wellbore | Wellbore Classification: GW AB - 8/28/2024 | | Wellbore Permit | DIRECTIONAL | | Permit #: | | Expiration Date: | 9/7/2012 | | Proposed Top PZ Location: | Sec:26 Twp: 2N 66W | Footage: 61 FNL 1333 FWL | | Bottom Hole Location: | Sec:26 Twp: 2N 66W | Footage: 36 FNL 1312 FWL | | Proposed Depth/Form: | 8382 ft. | | Surface Mineral Owner Same: | No | | Mineral Owner: | FEE | Surface Owner: | FEE | | Unit: | | Unit Number: | | | Formation And Spacing: | Code: CODL , Formation: CODELL , Order: 407 , Unit Acreage: 160, Drill Unit: GWA | | Formation And Spacing: | Code: JSND , Formation: J SAND , Order: 232 , Unit Acreage: 160, Drill Unit: GWA | | Formation And Spacing: | Code: NBRR , Formation: NIOBRARA , Order: 407 , Unit Acreage: 160, Drill Unit: GWA | | Casing: | String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: , Depth: 1100 ft., Weight: 24 , Citings Type: PLANNED | | Cement: | Sacks: 470, Top: 0 ft., Bottom: 1100 ft. | | Casing: | String Type: 1ST, Hole Size: 7.875 in., Size: 4.5 in., Top: , Depth: 8382 ft., Weight: 11.6 , Citings Type: PLANNED | | Cement: | Sacks: 290, Top: 7277 ft., Bottom: 8382 ft. |
| | |
| Wellbore Completed | | Completion Date: | 8/30/2011 | | Spud Date: | 8/24/2011 | Spud Date Is: | ACTUAL | | Measured TD: | 8383 ft. | Measured PB depth: | 8364 ft. | | True Vertical TD: | 8120 ft. | True Vertical PB depth: | 8101 ft. | | Top PZ Location: | Sec:26 Twp: 2N 66W | Footage: 61 FNL 1333 FWL | | Bottom Hole Location: | Sec:26 Twp: 2N 66W | Footage: 36 FNL 1312 FWL | | Log Types: | CBL 1670903 | | Casing: | String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: 0 ft., Depth: 1135 ft., Weight: 24 , Citings Type: ACTUAL | | Cement: | Sacks: 400, Top: 0 ft., Bottom: 1135 ft., Determination Method: VISU | | Casing: | String Type: 1ST, Hole Size: 7.875 in., Size: 4.5 in., Top: 0 ft., Depth: 8374 ft., Weight: 11.6 , Citings Type: ACTUAL | | Cement: | Sacks: 610, Top: 4230 ft., Bottom: 8374 ft., Determination Method: CBL | | Formation | Interval Top | Log Bottom | Cored | DSTs | | SUSSEX | 5016 ft. | | | | | NIOBRARA | 7521 ft. | | | | | CODELL | 7817 ft. | | | | | J SAND | 8271 ft. | | | |
Formation JSND Formation Classification: GW Status: AB - 8/28/2024 Interval Top: 8271 ft. Interval Bottom: 8310 ft.| Completed Information for Formation J SAND | | 1st Production Date: | N/A | Choke Size: | | | Formation Name: | J SAND | Commingled: | No | | Production Method: | | | Open Hole Completion: | No |
| | Formation Treatment | | Treatment Date: | 9/13/2011 | | Treatment Summary: | J SAND COMPLETION. FRAC'D THE J-SAND 8271'-8310', (78 HOLES) W/62,160 GAL 18 # VISTAR HYBRID CROSS LINKED GEL CONTAINING 250,340# 20/40 SAND. 09/13/11.
|
| | Tubing Size: | | Tubing Setting Depth: | | | Tubing Packer Depth: | | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | No Initial Test Data was found for formation JSND. |
| | Perforation Data: | | Interval Top: | 8271 ft. | # Of Holes: | 78 | | Interval Bottom: | 8310 ft. | Hole Size: | |
|
Formation CODL Formation Classification: GW Status: CM - 7/2/2024 Interval Top: 7817 ft. Interval Bottom: 7835 ft.| Completed Information for Formation CODELL | | 1st Production Date: | N/A | Choke Size: | | | Formation Name: | CODELL | Commingled: | Yes | | Production Method: | | | Open Hole Completion: | No |
| | Tubing Size: | | Tubing Setting Depth: | | | Tubing Packer Depth: | | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | No Initial Test Data was found for formation CODL. |
| | Perforation Data: | | Interval Top: | 7817 ft. | # Of Holes: | 36 | | Interval Bottom: | 7835 ft. | Hole Size: | |
|
Formation JNBCD Formation Classification: GW Status: CM - 12/3/2011 Interval Top: 7588 ft. Interval Bottom: 8310 ft.| Completed Information for Formation J-NIOBRARA-CODELL | | 1st Production Date: | 10/21/2011 | Choke Size: | | | Formation Name: | J-NIOBRARA-CODELL | Commingled: | | | Production Method: | | | Open Hole Completion: | |
| | Formation Treatment | | Treatment Date: | 12/3/2011 | | Treatment Summary: | JSND-CDL-NBRR COMMINGLE. SET CBP @ 7520’. 11/28/11. DRILLED OUT CBP @ 7520’, CFP @ 7660’, CFP @ 7890' TO COMMINGLE THE JSND-CDL-NBRR. 11/29/2011. |
| | Tubing Size: | 2.375 in. | Tubing Setting Depth: | 8243 ft. | | Tubing Packer Depth: | | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | Initial Test Data: | | Test Date: | 12/3/2011 | Test Method: | FLOWING | | Hours Tested: | 24 | Gas Type: | DRY | | Gas Disposal: | SOLD | |
| Test Type | Measure |
|---|
| BBLS_H2O | 10 | | BBLS_OIL | 50 | | BTU_GAS | 1289 | | CALC_BBLS_H2O | 10 | | CALC_BBLS_OIL | 50 | | CALC_GOR | 7680 | | CALC_MCF_GAS | 384 | | CASING_PRESS | 1224 | | GRAVITY_OIL | 1 | | MCF_GAS | 384 | | TUBING_PRESS | 384 |
| | Perforation Data: | | Interval Top: | 7588 ft. | # Of Holes: | 230 | | Interval Bottom: | 8310 ft. | Hole Size: | |
|
Formation NB-CD Formation Classification: GW Status: AB - 8/28/2024 Interval Top: 7588 ft. Interval Bottom: 7835 ft.| Completed Information for Formation NIOBRARA-CODELL | | 1st Production Date: | N/A | Choke Size: | | | Formation Name: | NIOBRARA-CODELL | Commingled: | No | | Production Method: | | | Open Hole Completion: | No |
| | Formation Treatment | | Treatment Date: | 9/13/2011 | | Treatment Summary: | CDL-NBRR COMPLETION. SET CFP @ 7890’. 09/13/2011. FRAC’D THE CODELL 7817’-7835’, (36 HOLES) W/87,150 GAL 22 # VISTAR HYBRID CROSS LINKED GEL CONTAINING 250,500# 20/40 SAND. 09/13/1.
SET CFP @ 7660’ 9/13/11. FRAC’D THE NIOBRARA 7588’-7617’, (116 HOLES), W/98,784 GALS 18# VISTAR HYBRID CROSS LINKED GEL CONTAINING 252,360# 20/40 SAND. 09/13/2011. |
| | Tubing Size: | | Tubing Setting Depth: | | | Tubing Packer Depth: | | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | No Initial Test Data was found for formation NB-CD. |
| | Perforation Data: | | Interval Top: | 7588 ft. | # Of Holes: | 152 | | Interval Bottom: | 7835 ft. | Hole Size: | |
|
Formation NBRR Formation Classification: GW Status: CM - 7/2/2024 Interval Top: 7588 ft. Interval Bottom: 7617 ft.| Completed Information for Formation NIOBRARA | | 1st Production Date: | N/A | Choke Size: | | | Formation Name: | NIOBRARA | Commingled: | Yes | | Production Method: | | | Open Hole Completion: | No |
| | Tubing Size: | | Tubing Setting Depth: | | | Tubing Packer Depth: | | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | No Initial Test Data was found for formation NBRR. |
| | Perforation Data: | | Interval Top: | 7588 ft. | # Of Holes: | 116 | | Interval Bottom: | 7617 ft. | Hole Size: | |
|
|
|
|
|
|
|
| Reported Plugged | Y | 08/28/2024 |
| Out Of Service Repurposed | N | |
| Out Of Service | Y | Plugging Due Date 05/23/2028 |
| Inactive Exception | N | |
| Noticed Inactive | N | |
| Defined Inactive | N | |
| Low Producing | N | |
| Total Oil Produced (Barrels) | 0 |
| Total Gas Produced (MCF) | 0 |
| GOR | |
| GOR Determination | |
| Average BOE per Day | 0.000 |
| Average MCFE per Day | 0.000 |
| Federal Financial Assurance | i | |
|
|