Wellbore #00 Wellbore Classification: ERIW Status: IJ - 12/1/2022 Measured TD: 5760 ft.| Wellbore Data for Original Wellbore | Wellbore Classification: ERIW IJ - 12/1/2022 | | Wellbore Permit | | | Permit #: | | Expiration Date: | 3/1/2020 | | Proposed Depth/Form: | 5760 ft. | | Surface Mineral Owner Same: | No | | Mineral Owner: | FEE | Surface Owner: | FEE | | Unit: | | Unit Number: | | | Formation And Spacing: | Code: DSND , Formation: D SAND , Order: 26-60 , Unit Acreage: 1200, Drill Unit: | | Formation And Spacing: | Code: JSND , Formation: J SAND , Order: , Unit Acreage: , Drill Unit: | | Casing: | String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: 0 ft., Depth: 138 ft., Weight: 24 , Citings Type: PLANNED | | Cement: | Sacks: 100, Top: 0 ft., Bottom: 138 ft. | | Casing: | String Type: 1ST, Hole Size: 7.875 in., Size: 5.5 in., Top: 0 ft., Depth: 5756 ft., Weight: 15.5 , Citings Type: PLANNED | | Cement: | Sacks: 225, Top: 4600 ft., Bottom: 5756 ft. |
| | |
| Wellbore Completed | | Completion Date: | 12/15/1984 | | Spud Date: | 12/8/1984 | Spud Date Is: | ACTUAL | | Measured TD: | 5760 ft. | Measured PB depth: | 5745 ft. | | True Vertical TD: | | True Vertical PB depth: | | | Log Types: | Two new logs were run during this conversion to an enhanced recovery well: (1) a CBL across the D and J sand interval on 12/5/2012 and (2) a CBL across the remedial cement interval (surface to 250') on 3/8/2013. Both logs have been submitted in digital and hardcopy formats. | | Log Types: | CBL | | Casing: | String Type: SURF, Hole Size: 12.25 in., Size: 8.625 in., Top: 0 ft., Depth: 138 ft., Weight: 24 , Citings Type: ACTUAL | | Cement: | Sacks: 100, Top: 0 ft., Bottom: 138 ft., Determination Method: VISU | | Casing: | String Type: 1ST, Hole Size: 7.875 in., Size: 5.5 in., Top: 0 ft., Depth: 5746 ft., Weight: 15.5 , Citings Type: ACTUAL | | Cement: | Sacks: 225, Top: 4600 ft., Bottom: 5746 ft., Determination Method: CBL | | Casing: | String Type: 2ND, Hole Size: 5 in., Size: 4.5 in., Top: 0 ft., Depth: 5722 ft., Weight: 11.6 , Citings Type: ACTUAL | | Cement: | Sacks: 145, Top: 0 ft., Bottom: 5722 ft., Determination Method: VISU | | Additional Cement: | String Type: 1ST , Top: 24 ft., Depth: 252 ft., Bottom: 252 ft., Sacks: 70, Method: 1 INCH | | Formation | Interval Top | Log Bottom | Cored | DSTs | | NIOBRARA | 4743 ft. | | | | | GREENHORN | 5257 ft. | | | | | GRANEROS | 5340 ft. | | | | | BENTONITE | 5502 ft. | | | | | D SAND | 5595 ft. | | | | | J SAND | 5667 ft. | | | |
Formation JSND Formation Classification: ERIW Status: IJ - 12/1/2022 Interval Top: 5670 ft. Interval Bottom: 5717 ft.| Completed Information for Formation J SAND | | 1st Production Date: | N/A | Choke Size: | | | Formation Name: | J SAND | Commingled: | No | | Production Method: | | | Open Hole Completion: | No |
| | Formation Treatment | | Treatment Type: | | | Treatment Date: | 7/31/2018 | Treatment End Date: | N/A | | Treatment Summary: | No treatment - J sand perfs at 5670-5698 and 5703-5717 w/ 6 spf | | Total fluid used in treatment (bbls): | | Max pressure during treatment (psi): | | | Total gas used in treatment (mcf): | | Fluid density (lbs/gal): | | | Type Of gas: | | Number Of staged intervals: | | | Total acid used in treatment (bbls): | | Min frac gradient (psi/ft): | | | Recycled water used in treatment (bbls): | | Total flowback volume recovered (bbls): | | | Fresh water used in treatment (bbls): | | Disposition method For flowback: | | | Total proppant used (lbs): | | Green completions techniques utilized: | -- | | Reason green techniques Not utilized: | | Formation Treatment | | Treatment Type: | | | Treatment Date: | 3/4/2013 | Treatment End Date: | N/A | | Treatment Summary: | No treatment of the J sand; the original J sand perforations were abandoned with a CIBP and 2 sacks of cement. | | Total fluid used in treatment (bbls): | | Max pressure during treatment (psi): | | | Total gas used in treatment (mcf): | | Fluid density (lbs/gal): | | | Type Of gas: | | Number Of staged intervals: | | | Total acid used in treatment (bbls): | | Min frac gradient (psi/ft): | | | Recycled water used in treatment (bbls): | | Total flowback volume recovered (bbls): | | | Fresh water used in treatment (bbls): | | Disposition method For flowback: | | | Total proppant used (lbs): | | Green completions techniques utilized: | -- | | Reason green techniques Not utilized: |
| | Tubing Size: | | Tubing Setting Depth: | | | Tubing Packer Depth: | | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | No Initial Test Data was found for formation JSND. |
| | Perforation Data: | | Interval Top: | 5670 ft. | # Of Holes: | 252 | | Interval Bottom: | 5717 ft. | Hole Size: | |
|
Formation DSND Formation Classification: ERIW Status: AB - 6/29/2018 Interval Top: 5614 ft. Interval Bottom: 5622 ft.| Completed Information for Formation D SAND | | 1st Production Date: | 4/29/2013 | Choke Size: | | | Formation Name: | D SAND | Commingled: | No | | Production Method: | | | Open Hole Completion: | No |
| | Formation Treatment | | Treatment Type: | ACID JOB | | Treatment Date: | 4/29/2013 | Treatment End Date: | 4/29/2013 | | Treatment Summary: | D sand perforated and acidized in preparation for conversion to a water injection well. Acid job was comprised of 750 gallons of 15% HCL and 250 gallons of 10% Acetic acid. Because the well is being converted to an injection well, there is no flowback associated with this acid job. | | Total fluid used in treatment (bbls): | 54 | Max pressure during treatment (psi): | 4866 | | Total gas used in treatment (mcf): | | Fluid density (lbs/gal): | | | Type Of gas: | | Number Of staged intervals: | | | Total acid used in treatment (bbls): | 24 | Min frac gradient (psi/ft): | | | Recycled water used in treatment (bbls): | 30 | Total flowback volume recovered (bbls): | | | Fresh water used in treatment (bbls): | | Disposition method For flowback: | | | Total proppant used (lbs): | | Green completions techniques utilized: | -- | | Reason green techniques Not utilized: |
| | Tubing Size: | | Tubing Setting Depth: | | | Tubing Packer Depth: | | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | No Initial Test Data was found for formation DSND. |
| | Perforation Data: | | Interval Top: | 5614 ft. | # Of Holes: | 48 | | Interval Bottom: | 5622 ft. | Hole Size: | 0.4 in. |
|
|
|
|
|
|
|
| Reported Plugged | N | |
| Out Of Service Repurposed | N | |
| Out Of Service | N | |
| Inactive Exception | N | |
| Noticed Inactive | N | |
| Defined Inactive (UIC) | Y | Last Use 07/31/2024 |
| Low Producing | N | |
| Total Oil Produced (Barrels) | 0 |
| Total Gas Produced (MCF) | 0 |
| GOR | |
| GOR Determination | |
| Average BOE per Day | 0.000 |
| Average MCFE per Day | 0.000 |
| Federal Financial Assurance | i | |
|
|