Wellbore #00 Wellbore Classification: OW Status: SI - 11/1/2025 Measured TD: 16582 ft. Vertical TD: 6195 ft.| Wellbore Data for Original Wellbore | Wellbore Classification: OW SI - 11/1/2025 | | Wellbore Permit | HORIZONTAL | | Permit #: | | Expiration Date: | 7/29/2020 | | Proposed Top PZ Location: | Sec:13 Twp: 7N 81W | Footage: 1073 FSL 625 FEL | | Bottom Hole Location: | Sec:12 Twp: 7N 81W | Footage: 100 FNL 736 FEL | | Proposed Depth/Form: | 16704 ft. | | Surface Mineral Owner Same: | No | | Mineral Owner: | FEE | Surface Owner: | FEE | | Unit: | | Unit Number: | | | Formation And Spacing: | Code: NBRR , Formation: NIOBRARA , Order: 531-57 , Unit Acreage: 640, Drill Unit: E/2: Sec 12 & 13 | | Casing: | String Type: CONDUCTOR, Hole Size: 26 in., Size: 16.25 in., Top: 0 ft., Depth: 90 ft., Weight: 42 , Citings Type: PLANNED | | Cement: | Sacks: 190, Top: 0 ft., Bottom: 90 ft. | | Casing: | String Type: SURF, Hole Size: 12.25 in., Size: 9.625 in., Top: 0 ft., Depth: 2400 ft., Weight: 36 , Citings Type: PLANNED | | Cement: | Sacks: 630, Top: 0 ft., Bottom: 2400 ft. | | Casing: | String Type: 1ST, Hole Size: 8.75 in., Size: 5.5 in., Top: 0 ft., Depth: 16704 ft., Weight: 20 , Citings Type: PLANNED | | Cement: | Sacks: 3000, Top: , Bottom: 16704 ft. |
| | |
| Wellbore Completed | | Completion Date: | 10/17/2018 | | Spud Date: | 9/7/2018 | Spud Date Is: | ACTUAL | | Measured TD: | 16582 ft. | Measured PB depth: | 16458 ft. | | True Vertical TD: | 6195 ft. | True Vertical PB depth: | 6205 ft. | | Top PZ Location: | Sec:13 Twp: 7N 81W | Footage: 1073 FSL 625 FEL | | Bottom Hole Location: | Sec:12 Twp: 7N 81W | Footage: 100 FNL 736 FEL | | Log Types: | MWD, CBL, Mud, (Triple Combo in 057-06584) | | Casing: | String Type: CONDUCTOR, Hole Size: 20 in., Size: 16 in., Top: 0 ft., Depth: 98 ft., Weight: 65 , Citings Type: ACTUAL | | Cement: | Sacks: 70, Top: 0 ft., Bottom: 98 ft., Determination Method: VISU | | Casing: | String Type: SURF, Hole Size: 12.25 in., Size: 9.625 in., Top: 0 ft., Depth: 2412 ft., Weight: 36 , Citings Type: ACTUAL | | Cement: | Sacks: 705, Top: 0 ft., Bottom: 2412 ft., Determination Method: VISU | | Casing: | String Type: 1ST, Hole Size: 8.75 in., Size: 5.5 in., Top: 0 ft., Depth: 16548 ft., Weight: 20 , Citings Type: ACTUAL | | Cement: | Sacks: 2805, Top: 2334 ft., Bottom: 16548 ft., Determination Method: CBL | | Formation | Interval Top | Log Bottom | Cored | DSTs | | LANCE | 2748 ft. | | | | | FOX HILLS | 3244 ft. | | | | | PIERRE | 3453 ft. | | | | | SUSSEX | 4361 ft. | | | | | SHANNON | 4908 ft. | | | | | MANCOS | 6137 ft. | | | | | NIOBRARA | 6495 ft. | | | |
Formation NBRR Formation Classification: OW Status: SI - 11/1/2025 Interval Top: 7595 ft. Interval Bottom: 15229 ft.| Completed Information for Formation NIOBRARA | | 1st Production Date: | 4/13/2019 | Choke Size: | | | Formation Name: | NIOBRARA | Commingled: | No | | Production Method: | | | Open Hole Completion: | No |
| | Formation Treatment | | Treatment Type: | FRACTURE STIMULATION | | Treatment Date: | 1/23/2019 | Treatment End Date: | 1/27/2019 | | Treatment Summary: | Plug & Perf Completion: The frac job contained 34 stages, all stimulated with water, acid, and proppant. The volume for each component was 845 bbls of 15% NEFE HCL Acid, 181,151 bbls of fluid, and 988,828 lbs of 40/70 and 7,522,362 lbs of 20/40 proppant.
| | Total fluid used in treatment (bbls): | 181151 | Max pressure during treatment (psi): | 8507 | | Total gas used in treatment (mcf): | | Fluid density (lbs/gal): | 8.43 | | Type Of gas: | | Number Of staged intervals: | 34 | | Total acid used in treatment (bbls): | 845 | Min frac gradient (psi/ft): | 0.53 | | Recycled water used in treatment (bbls): | | Total flowback volume recovered (bbls): | 23455 | | Fresh water used in treatment (bbls): | 180306 | Disposition method For flowback: | DISPOSAL | | Total proppant used (lbs): | 8511190 | Green completions techniques utilized: | -- | | Reason green techniques Not utilized: PIPELINE |
| | Tubing Size: | 2.875 in. | Tubing Setting Depth: | 6787 ft. | | Tubing Packer Depth: | 6776 ft. | Tubing Multiple Packer: | | | Open Hole Top: | | Open Hole Bottom: | | | Initial Test Data: | | Test Date: | 3/2/2019 | Test Method: | Flowing | | Hours Tested: | 24 | Gas Type: | WET | | Gas Disposal: | FLARED | |
| Test Type | Measure |
|---|
| BBLS_H2O | 1248 | | BBLS_OIL | 557 | | BTU_GAS | 1600 | | CALC_BBLS_H2O | 1248 | | CALC_BBLS_OIL | 557 | | CALC_GOR | 481 | | CALC_MCF_GAS | 268 | | CASING_PRESS | 1000 | | GRAVITY_OIL | 35 | | MCF_GAS | 268 | | TUBING_PRESS | 230 |
| | Perforation Data: | | Interval Top: | 7595 ft. | # Of Holes: | 1088 | | Interval Bottom: | 15229 ft. | Hole Size: | 0.42 in. |
|
|
|
|
|
|
|
| Reported Plugged | N | |
| Out Of Service Repurposed | N | |
| Out Of Service | N | |
| Inactive Exception | N | |
| Noticed Inactive | N | |
| Defined Inactive | N | |
| Low Producing | Y | Production Period 11/2024 - 10/2025 |
| Total Oil Produced (Barrels) | 78 |
| Total Gas Produced (MCF) | 26 |
| GOR | 333 |
| GOR Determination | BOE |
| Average BOE per Day | 0.230 |
| Average MCFE per Day | 1.325 |
| Federal Financial Assurance | i | |
|
|